pads with spacers for the estimated height requirement (see Table 3 on
page 10). It is recommended that the pads and spacers be put on while
the system is elevated by the fork lift. The system can be lowered on to
the pads and spacers, however this is extremely difficult to execute.
Table 2
Spacer Size Reference
Spacer
Spacer A (E7200-24715)
Spacer B (E7200-24717)
Spacer C (E7200-24716)
ADVICE
If the height of the system does not matter, it may be best to
install all the spacers so none become lost.
Check System Height and Position
10.
production line, adjust the system location such that the fixed rail
aligns with the production line conveyors. Markings will be on each
outer barrier frame to show where the stage position for loading and
unloading will be (see Figure 4). Use these markings to align height
and position of the 5DX with the customers line.
Verify that the system is level
11.
done by turning the top of the threaded shaft (see Figure 5). Use a
level inside the system on the granite base in various locations rather
than on the top of the system. Check x and y orientation in all 4
corners.
ADVICE
If the 5DX system is to be integrated into a production line, you may wish
to level and adjust height at the same time. Align the 5DX with the
production line using the lines marked on the outer barrier frame.
Agilent 5DX Installation
In Centimeters
In Inches
1.60 cm
0.630 in.
3.175 cm
1.25 in.
7.62 cm
3.0 in.
— If the 5DX is installed on a
— Adjust pads as required. This is
Quantity
4
8
4
9