System Hardware Installation and Setup

Site preparation and movement to the final location should be complete at
this point. Verify correct placement of the main unit, and subsystems (such
as the Electronics Bay, user interface and monitor) with your customer (see
Figure 6). Begin assembly of the 5DX system using the following
procedure:
Stage Release
1.
movement motors and assemblies inside the main cabinet. Remove
these to allow both X and Y movement.
Check Lead Panels
2.
edge of the granite. Check to make sure none have come loose during
shipment.
Inner Barrier Release
3.
the inner barrier. Each is held in place by three screws (see Figure 7).
Open the top sliding access panel on each side and remove these to
allow barrier movement. These parts may be discarded or recycled
after they are removed.
Caution
The screws also have washers. Be careful not to drop the bracket
screws or washers inside the 5DX.
14
— There are several tie wraps securing the stage,
— There are eight lead panels around the outer
— There are brackets mounted to both sides of
Agilent 5DX Installation