7.2.3 Starting the Ozone System Initially

The following steps must be carried out before initial commissioning:
1.
Check that all supply media for the system are available according to the technical data
(gas, cooling water, power).
2.
Check that the subsequent process technology for the ozone generated is ready to
accept it and can process it according to its purpose.
3.
Check that all safety equipment is available and enabled.
4.
Set all manual valves to operating position.
5.
Let the cooling water flow into the system and bleed the pipe work.
6.
Set the cooling water flow according to the instructions given in
7.
Switch on the ozone system.
Manual_SMOevoPLUS_eng_01.2019.doc
The system was tested at the manufacturer's factory
(Wedeco) and can be put into operation once it has been
integrated on site. A test of the ambient air sensor must be
carried out by Wedeco personnel or instructed staff before
the system is switched on for the first time.
Observe the initial starting up of the system carefully in order
to be able to detect any potential hazardous situations at an
early stage.
Make yourself familiar how to operate the touch panel.
Refer to Chapter Operation.
Manual Ozone Generating System SMOevo
Installation and Initial Start Up
PLUS
Chapter Technical
Data.