Connecting The Ozone System - Xylem WEDECO SMOevo PLUS Series Original Manual

Ozone generating system
Table of Contents

Advertisement

Mark all pipes carrying ozone and oxygen with appropriate labels or coat of paint.
Protect all lines against damage or tearing off.
Keep all piping and mounting parts carrying oxygen or ozone free from oil and grease.

7.1.7 Connecting the Ozone System

Before putting the ozone system into operation, carry out the following steps:
1.
Connect all system components.
2.
Check the system for horizontal position and equal load distribution of all supporting
points to avoid stress on the system.
3.
Ensure stress-free connection of the system to in-house piping for the gas pipes.
4.
Ensure stress-free connection of the system to in-house piping for the cooling water.
5.
Carry out electrical connections in compliance with locally applicable regulations.
6.
Retighten all contact screws.
7.
Ground the ozone system.
8.
Connect the ozone system to the in-house electrical lines.
9.
Check the connected piping for leak tightness.
10. Ensure that no cooling liquid may flow back into the ozone system.
11. Activate the ambient air monitoring system.
12. Ensure that unused ozone or residual ozone is discharged by means of a residual
ozone destruction system.
Manual_SMOevoPLUS_eng_01.2019.doc
Refer to Chapter Technical Data and the Wiring Diagrams in the
Appendix. All connections must be carried out according to the
specifications.
The check of the ozone containing pipes must be carried out
according to the Pressure Equipment Directive by a qualified
person and documented in an appropriate report.
Manual Ozone Generating System SMOevo
Installation and Initial Start Up
PLUS
page 74 of 179