7.2 Initial Start-Up

7.2.1 Safety Instructions

Gas containing ozone in system components and pipes!
Even during the initial start-up ozone is generated. Hazard of toxic effects
and breathing difficulties.
Fire hazard (strongly oxidizing.)
If you smell ozone:
Immediately set the power switch to 0.
Leave the operating room while observing the safety measures.
Do not smoke and avoid open flames.
It is essential to follow the guidelines for handling ozone.
Refer to section Safety.
After thoroughly ventilating the operating room with the converter
switched off (no ozone production), look for the cause of the leak.
Maybe not all the connections are sufficiently tightened. Although the
system was factory tested, connections might have loosened during
transport.
Escaping oxygen!
Fire hazard (strongly oxidizing)
Ensure sufficient room ventilation.
Do not smoke and avoid open flames.
It is essential to follow the guidelines for handling oxygen.
Refer to section Safety.

7.2.2 Requirements for the Commissioning Staff

The ozone system may be commissioned by qualified persons only.
Classification of Operating Staff
Manual_SMOevoPLUS_eng_01.2019.doc
WARNING!
WARNING!
The initial start-up always takes place in manual mode.
Make sure that the system has been given enough time to adapt
to the climatic conditions of the location before it is activated for
the first time.
.
Manual Ozone Generating System SMOevo
Installation and Initial Start Up
PLUS
Refer to Chapter
page 76 of 179

Advertisement

Table of Contents
loading

Table of Contents