Capacity Test - Huawei UPS5000-E-400K-SM User Manual

Hide thumbs Also See for UPS5000-E-400K-SM:
Table of Contents

Advertisement

UPS5000-E-(350 kVA-800 kVA)
User Manual (50 kVA Power Modules)
----End

5.6.3 Capacity Test

Context
Before a capacity test, ensure that:
Procedure
Step 1 On the main screen of the LCD, tap System Info. Tap
displayed.
Step 2 On the Maintenance screen, tap Battery Maint..
Step 3 Tap Start next to Capacity Test to start a capacity test.
Issue 05 (2018-01-08)
When the battery test is complete, the test data is used as common test data. Record the data obtained
from the latest five tests.
The shallow discharge test automatically stops in any of the following cases:
The battery discharge capacity reaches the specified value (10%–50%, 20% by default).
The discharge voltage reaches the warning threshold (calculated in real time).
The load ratio fluctuation exceeds 10%.
An alarm is generated.
The UPS is working in normal mode; float charging or hibernation has lasted for 2 hours
after the state of charge (SOC) reaches 100%; and the load ratio fluctuation is less than
10%.
The UPS has generated no battery overtemperature, overvoltage, or overcurrent alarm. No
generator is connected to the UPS.
The mains, batteries, charger, and discharger are normal. No overload alarm is generated.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
5 Operations
. The Maintenance screen is
255