3.2.1.2 Installing the UPS on Channel Steel

Context
Procedure
Step 1 Determine the cabinet installation positions on the channel steel based on holes in the
marking-off template for channel steel installation.
Figure 3-28 Mounting hole dimensions for the 400 kVA UPS and 500 kVA UPS (unit: mm)
Issue 05 (2018-01-08)
Channel steel and expansion bolts for securing the channel steel should be purchased by
the customer. The recommended channel steel width is 50 mm or more.
Ensure that the spacing between external sides of a channel steel is 800 mm. Secure
channel steel to the ground by using expansion bolts.
Cabinet mounting holes must be aligned with channel steel mounting holes, and secure the
cabinet to channel steel with bolts.
Keep the channel steel surface flat.
A: mounting holes on the channel steel
B: mounting holes on the floor
Huawei Proprietary and Confidential