6. Remove the cap from fitting (A).
7. Remove the plug from hose (B). Install hose to fitting (A)
as shown.
8. Install steel line (A) (MD #246954) from port A on the
completion assembly to tee fitting (D).
9. Install steel line (B) (MD #247335) from port B on the
completion assembly to tee fitting (C).
10. Attach hose (A) (MD #247781) to steel line connecting to
port D of transport swing control.
11. Attach hose (B) (MD #247781) to steel line connecting to
port C of transport swing control.
12. Secure hoses (A) and (B) together with a cable tie
(MD #30753).
NOTE:
Ensure that direction arrow on check valve (C) points
toward tee fitting.
214633
INSTALLATION INSTRUCTIONS
Figure 3.40: Alignment Valve Fitting
Figure 3.41: Completion Assembly Plumbing
Figure 3.42: Transport Swing Cylinder
28
B
A
C
D
A
B
C
A
B
Revision C