To start the run and view its progress, follow the steps below:
1. Tap Next in the Load the tip rack step. The Run setup selection overview dialog is shown.
Figure 63. Run setup selection overview dialog.
2. If all the information in the overview is correct, tap Create favorite to save the protocol to your
favorites, or tap Start to immediately proceed with the protocol run. To make modifications to
any of the selections, tap Return to go back to the run setup.
Note: The Estimated run time does not include the time to complete the Load Check.
3. If the hood of the instrument is open, close it and tap Proceed.
Figure 64. Close the hood dialog.
4. For EZ2 Connect Fx: If your instrument has a built-in camera, a load check is performed. For
more information about the load check, refer to the Load check section. The run will start after
the check is completed. To stop the load check, tap Abort.
EZ2 Connect and EZ2 Connect Fx User Manual 09/2021
92