Mcb Opening Timing Diagram; Maintenance Recommendation - ABB ACS6000 User Manual

System drives
Hide thumbs Also See for ACS6000:
Table of Contents

Advertisement

1
2
(1) Short-circuit occurs
(2) Open and or trip command is set at the drive control output
(3) No further damage to the drive
(4) No hazard to personnel
(5) Maximum protection trip time
(6) Maximum safety trip time
In order to meet the stipulated safety requirements, ABB recommends one
of the following:
• MCB is equipped with 2 independent opening coils
• MCB is equipped with an opening coil and an undervoltage coil for
monitoring of the control voltage
• Upstream protection coordination scheme is provided which uses
the "breaker failure" (ANSI 50BF) signal to automatically trip the
upstream breaker, in case the MCB does not open.
IMPORTANT! The upstream breaker must open within the maximum
safety trip time after a failure has occurred.
2.8

Maintenance recommendation

The MCB trip circuits should be checked annually.
3BHS212794 E01 REV M
3
5
Figure 2-3 MCB opening timing diagram
ACS6000 USER MANUAL
02 IMPORTANT SAFETY INFORMATION
6
4
49/278