System Tests and Adjustments
The N5290/1A Millimeter Test System Preliminary Check
4. When finished, the following dialog box is displayed. Remove the load and
Figure 3-5
Millimeter Installation Cal – Dialog Box Load Calibration "Finish"
5. The following dialog box is displayed until the calibration is finished (i.e., It
Figure 3-6
Millimeter Installation Cal – Dialog Box Open–circuit Calibration Ongoing/
"Finish"
6. If prompted, repeat steps
The Head Cable Checks
A faulty test port cable can cause a failure in the verification test. The following
checks are not required, but are recommended to verify the performance of the
test port cable. These checks verify the integrity of the head cables that
connect to the N5292A test set.
—
Accessories Used in the Head Check
Keysight N5290/1A Service Guide
press Finish. Refer to
Figure 3-5 on page
is not necessary to connect a calibration kit open for this step. Refer to
Figure 3-6 on page
3-11.
calibration.
"Head Cable Stability Check" on page 3-12
3-11.
3
through
5
for all of the other ports requiring