UPS5000-A-(200 kVA-800 kVA)
User Manual
Figure 3-29 Hole dimensions (600K, unit: mm)
Step 2 Drill cabinet mounting holes in channel steel by using a hammer drill.
Step 3 Use a pallet truck to move the cabinet to the installation position.
Step 4 Use common M12x45 bolts to secure the cabinets into the mounting holes in the channel steel
and tighten the bolts.
Step 5 Install the front, rear, left, and right anchor baffle plates.
----End

3.2.3 Installing UPS Cabinets (800K)

3.2.3.1 Installing the UPS on the Floor

Determining the UPS Installation Position
Step 1 Determine the cabinet installation positions on the ground based on holes in the marking-off
template for ground installation.
Issue 03 (2019-02-15)
Ensure that the installation floor is flat.
The marking-off template is delivered with the UPS.
A: mounting holes on the channel steel
B: mounting holes on the floor
Copyright © Huawei Technologies Co., Ltd.