Figure 5-17 Starting a capacity test
----End

5.6.4 Test Data Download

Procedure
Step 1 On the WebUI, choose Query > Logs, choose logs that need to be exported from the Log
drop-down list box, and click Query.
Figure 5-18 Logs
Step 2 Choose logs that have been queried from the Log drop-down list box, and click Export.
----End
Issue 03 (2019-02-15)
The capacity test automatically stops in any of the following cases:
The battery discharge voltage reaches the end of discharge (EOD) voltage plus 0.01 V.
The load fluctuation exceeds 10%.
An alarm is generated.
When the battery discharge voltage reaches the EOD voltage plus 0.01 V, the test is complete. The test
data is used as capacity test data. Save the capacity test data record with the largest discharge capacity in
a month as the capacity test data for the month. A maximum of recent 36 capacity test records can be
saved.
Copyright © Huawei Technologies Co., Ltd.