Page 1
UPS5000-A-(200 kVA-800 kVA) User Manual Issue Date 2020-04-27 HUAWEI DIGITAL POWER TECHNOLOGIES CO., LTD.
Page 2
Notice The purchased products, services and features are stipulated by the contract made between Huawei Digital Power Technologies Co., Ltd. and the customer. All or part of the products, services and features described in this document may not be within the purchase scope or the usage scope. Unless otherwise specified in the contract, all statements, information, and recommendations in this document are provided "AS IS"...
Page 65
NO TE ● The ECM expansion subrack does not support onsite installation. If you require this optional component, inform Huawei when you purchase the UPS so that Huawei can install the subrack before delivery. ● IP21 components cannot be configured for the UPS5000-A-300K-STT or UPS5000- A-200K-FT.
Page 67
● If an IP21 component is installed, cables cannot be routed from the top of the cabinet. ● The ECM expansion subrack does not support onsite installation. If this component is required, inform Huawei before purchasing the UPS to receive pre-installation services. Issue 05 (2020-04-27)
(if any) extension pole and power cables to avoid friction. 3.2.15 Remote EPO NO TICE ● Huawei does not provide the EPO switch or cable. If the cable is required, the recommended cable is 22 AWG. ● Equip the EPO switch with a protective cover to prevent misoperations, and cover the cable with protective tubing.
3.3.2 Connecting Power Cables (200K, 300K) Context The parallel power cables for different UPS models are connected in the same way. The UPS5000-A-200K-ST is used as an example. Procedure Step 1 Ground each UPS in a parallel system separately, and connect power cables and battery cables by referring to the section "Single UPS Installation."...
Step 1 Close the upstream bypass and mains input switches. Step 2 (Full configuration model) Close the UPS bypass input switch, mains input switch, and output switch. After the UPS is powered on, initialization begins. The MDU displays the Huawei logo and an initialization progress bar. ----End 4.1.2 Initial Startup...
Step 4 Press and hold down the BATT START button on the bypass unit for at least 2 seconds. The system automatically enters the battery cold start status. The LCD displays the Huawei logo and an initialization progress bar. Step 5 After LCD initialization, start the inverter on the LCD.
Customers are not allowed to maintain components behind protective covers that can be removed only using tools. If the components are to be maintained, contact Huawei technical support. ● Only maintenance engineers can maintain power units and bypass units.