Configure Connect IT using the web user interface
3. Expand the System section.
4. Expand the Scheduled tasks section.
5. In the Reboot time field, enter the time at which the Connect IT should reboot every day. If the
Connect IT is unable to synchronize its time with an NTP server, the Connect IT automatically
reboots after 24 hours of uptime. The syntax for this field is: HH:MM
6. Click Save at the bottom of the screen to save the changes.
Schedule system maintenance from the web UI
You can schedule the system to run a set of system maintenance tasks to run within a specified time
window. You can also schedule a custom script to run at the specified time and frequency.
Note
If you are scheduling a custom script, you must have previously created the script.
For example, you can specify a start time of 10:00 and a duration window of 2 hours. In this example,
the system maintenance can take place and custom scripts run at any time between 10:00 and 12:00.
1.
Log in to the Connect IT web
2. Click Configuration in the left pane.
3. Expand the System section.
4. Expand the Scheduled tasks section.
5. Enter values into the fields.
Field
Start time
Digi Connect IT® 16/48 User Guide
Schedule system maintenance from the web UI
UI.
Description
The start time of the maintenance window. All enabled
maintenance tasks take place at any random time within
the time block specified in the Duration window field.
If this field is empty, maintenance is not scheduled and no
maintenance tasks will run.
Syntax: HH:MM
If the duration in the Duration window field is set to 1 or
more hours, the minutes field is truncated.