Installation - Agilent Technologies VS Series Operation Manual

Helium mass spectrometer leak detectors
Hide thumbs Also See for VS Series:
Table of Contents

Advertisement

VS Series Helium Mass Spectrometer Leak Detectors

1.3 Installation

Installation requirements are described in Table 1-2.
Item
Leak Detector Location
Power
Mains Supply Voltage Fluctuations Must not exceed ±10% of the nominal voltage.
Pollution
Fixed Mains Socket Outlet
Table 1-2 Installation Requirements
Close to its power source.
Four inch clearance for proper ventilation.
Sufficient room for the operator to safely maneuver to
perform testing.
Either (depends on configuration ordered):
100 VAC, 50 Hz, 20 A
115 VAC, 60 Hz, 20 A or
230 VAC, 50/60 Hz, 12 A (models PR, MR and MD)
230 VAC, 50 Hz, (model PD03)
Pollution Degree 2 per EN61010-1 Standard.
Connect to a building protective earthing system.
Requirement
Additional ventilation requirements for
your specific application are discussed in
Section 1.3.2 "Recommended Additional
Services" on page 1-16.
When installing a bench system with a
mechanical pump, the power cord for that
pump, if connected to the back of the leak
detector, cannot exceed three meters.
Additionally, connect the mechanical pump
to the leak detector using the shortest
possible vacuum connection to maximize
vacuum performance.
1-9

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents