Commissioning guidelines

Overview
Converter with the control units CU240D-2
Operating Instructions, 04/2018, FW V4.9 SP10, A5E34262100B AF
Commissioning
5.2 Commissioning guidelines
1. Define the requirements to be
met by the drive for your
application.
(Page 84)
2. Restore the factory settings of
the inverter if necessary.
(Page 97)
3. Check if the factory setting of the
inverter is sufficient for your
application.
(Page 84)
4. Set the following for quick
commissioning of the drive:
– The closed-loop motor control
– The inputs and outputs
– The fieldbus interface
(Page 88)
5. Check if additional inverter
functions are required for the
application.
(Page 101)
6. If necessary, adapt the drive.
(Page 101)
7. Save your settings.
(Page 245)