Commissioning
5.1
Commissioning guidelines
Overview
SINAMICS G120C converter
Operating Instructions, 07/2015, FW V4.7 SP3, A5E34263257B AC
1. Define the requirements of your
application placed on the drive.
→ (Page 90) .
2. Reset the inverter when
required to the factory setting.
→ (Page 121) .
3. Check whether the factory
setting of the inverter is already
sufficient for your application.
4. When commissioning the drive,
set the following:
– The closed-loop motor
control
– The inputs and outputs
– The fieldbus interface
5. When required, adapt the drive
→ (Page 127).
6. Back up your settings
→ (Page 283).