INITIAL PEDESTAL INSTALLATION

1. CONCRETE PAD REQUIREMENTS
The location, dimensions, and composition of the
concrete pad underlying the pedestal should always
adhere to local building codes. The following
dimensions are minimum recommended values.
Always verify that installation plans adhere to local
code requirements prior to proceeding.
a. The pad area must be a minimum of 18" to a
side.
b. The concrete must be poured a minimum depth
of 18".
c. If there is no bumper block, the center of the
pedestal base should be situated 36" behind the
curb.
d. If a bumper block is in place, the center of the
pedestal base should be situated 12" behind the
curb.
e. WARNING: Pull wires an extra 5 feet
from conduit in order to facilitate

installation.

2. ANCHOR BOLT PLACEMENT
a. A cardboard base template is provided within the ProMountDuo™ internal packaging. This template
can be punched out from either the Base or the Cap cardboard boxes.
b. A minimum of four (4) anchor bolts must be embedded in the concrete pad for the purposes of securing
the pedestal post. The pedestal base is designed for anchor bolts to be centered in an approximately 6.5"
x 1.75" rectangular pattern as shown in Figure 6.
c. The anchor bolts, nuts and washers used for the
installation of the pedestal base are not included in
the pedestal kit and must be purchased separately.
Either 3/8", 1/2", or 5/8" anchor bolts can be used.
Always check against local building codes as they
may vary.