INSTALLATION REQUIREMENTS AND CONFIGURATIONS

Refer to the EVSE documentation to determine the appropriate circuit breaker
current capacity. All conductors must be appropriately sized for the EVSE
current capacity, in accordance with local and national electrical codes.
CONFIGURATION A:
Required Equipment for a Single-Mount Pedestal with one
ClipperCreek HCS EVSE (One EVSE per Pedestal):
One (1) ClipperCreek ProMountDuo™ Kit, ClipperCreek part number
0300-00-025.
One (1) ClipperCreek HCS EVSE, part number is determined by amperage
and options selected.
One (1) dedicated 208 or 240V AC branch circuit.
One (1) circuit breaker appropriately sized for the EVSE charging capacity.
Two (2) Live Line conductors that are appropriately sized based on the
EVSE power requirements (5 feet of length is adequate).
One (1) Ground Line conductor with enough length to comfortably pull all
the way through and above the top of the pedestal (5 feet is adequate).
Conduit sized to fit all Live Line and Ground Line conductors.
Four (4) Anchor Bolts with Nuts and Washers (additional washers may be
required for leveling)
CONFIGURATION B:
Required Equipment for a Dual-Mount Pedestal with two
ClipperCreek HCS EVSE (Two EVSE per Pedestal):
One (1) ClipperCreek ProMountDuo™ Kit, ClipperCreek part number
0300-00-025.
Two (2) ClipperCreek HCS EVSE, part numbers are determined by
amperage and options selected.
Two (2) dedicated 208 or 240V AC branch circuits.
Two (2) circuit breakers, appropriately sized with respect to the charging
capacity of each EVSE.
Two pairs (2x2) Live Line conductors (one pair for each EVSE) that are
appropriately sized based on the EVSE power requirements (5 feet of length
is adequate).
Two (2) Ground Line conductors (one for each EVSE) or a single bonded
Ground Line with enough length to comfortably pull all the way through and
above the top of the pedestal (5 feet is adequate).
Conduit sized to fit all Live Line and Ground Line conductors.
Four (4) Anchor Bolts with Nuts and Washers (additional washers may be
required for leveling)
ProMountDuo™ PEDESTAL INSTALLATION GUIDE
Page 11
ClipperCreek
CONFIGURATION A
Single ClipperCreek
HCS EVSE
CONFIGURATION B
Dual ClipperCreek
HCS EVSE
, Inc.

Advertisement

Table of Contents
loading

Table of Contents