ProMountDuo™ PEDESTAL INSTALLATION GUIDE
ClipperCreek
, Inc.
INITIAL PEDESTAL INSTALLATION
3. MOUNT THE PEDESTAL BASE
Once the concrete pad with anchor bolts
has been prepared and the three service
conductors have been pulled through the
underground conduit, the Pedestal Base (A)
may be placed.
a. Feed the three service conductors up
through the inside of the large center hole
in the Pedestal Base (A). The conductors
must be of sufficient length to pass
beyond the top of the pedestal so that
final connections can be worked with
comfortably at a later step.
b. Leveling adjustments must be made at
this time. Washers (not included) can be
used under the Base for leveling and/or
to prevent water accumulation.
c. Align the four Pedestal Base obround
holes with the four anchor bolts and ease
into place.
d. Secure the Pedestal Base to the concrete
anchor bolts using appropriately sized
nuts and washers (not included) as shown
in Figure 7.
e. Tighten the Anchor Bolts as much as
possible. See Figure 8.
(continued)