3.5.1
Single-Phase Power
Caution – Equipment damage – Each outlet must be in a circuit ranging from 200 to 240
VAC (30 A) and only be used for a power cord. An outlet to which a power cord is
connected must be grounded.
1. Before connecting a power cord, confirm that the main line switch on the ACS of the
server is switched off.
2. Using a multimeter, verify that the input power fulfills power requirements.
For details, see
3. Connect the plug of each power cord to a dedicated outlet.
3.5.2
Three-Phase Power
Using a multimeter, verify that the input power fulfills power requirements.
For details, see
3.6
Setting and Checking the Required
Information for the Servers
Before powering on the server, perform the initial setting of XSCF.
This section explains how to specify and check the required server information.
Note – To operate the XSCF Shell, use the console that was connected following the steps
indicated in
Section 3.6.1, "Switch On the Main Line Switches" on page 3-50
■
Section 3.6.2, "Logging Into the XSCF Shell" on page 3-51
■
Section 3.6.3, "Initializing the XSCF" on page 3-52
■
Section 3.6.4, "Checking for a Capacity on Demand (COD) Board" on page 3-53
■
Section 2.2.2.2, "Power Supply Requirements" on page
Section 2.2.2.2, "Power Supply Requirements" on page
Section 3.4.4, "Connecting the Administration Console" on page
2-6.
2-6.
3-46.
Chapter 3 Installing the Server
3-49
Need help?
Do you have a question about the SPARC Enterprise M9000 and is the answer not in the manual?