GE 750 Instruction Manual page 95

Feeder management relay
Hide thumbs Also See for 750:
Table of Contents

Advertisement

Using EnerVista Viewpoint with the 750/760
GE Multilin
9.
Click the Read Order Code button to connect to the 750/760 device and
upload the order code. If an communications error occurs, ensure that
communications values entered in the previous step correspond to the relay
setting values.
10. Click OK when complete.
11. From the EnerVista main window, select the IED Dashboard item to open the
Plug and Play IED dashboard. An icon for the 750/760 will be shown.
FIGURE 4–10: 'Plug and Play' Dashboard
12. Click the Dashboard button below the 750/760 icon to view the device
information. We have now successfully accessed our 750/760 through EnerVista
Viewpoint.
http://www.GEmultilin.com
750/760
Feeder Management Relay