Connecting EnerVista 750/760 Setup to the Relay
Connecting to the
Relay
NOTE
GE Multilin
Now that the communications parameters have been properly configured, the user
can easily communicate with the relay.
1.
Expand the Site list by double clicking on the site name or clicking on the «+»
box to list the available devices for the given site (for example, in the
"Substation 1" site shown below).
2.
Desired device trees can be expanded by clicking the «+» box. The following list
of headers is shown for each device:
Device Definitions
Settings
Actual Values
Commands
Communications
3.
Expand the Settings > Relay Setup list item and double click on Front Panel to
open the Front Panel settings window as shown below:
FIGURE 4–5: Main Window After Connection
4.
The Front Panel settings window will open with a corresponding status indicator
on the lower left of the EnerVista 750/760 Setup window.
5.
If the status indicator is red, verify that the serial or Ethernet cable is properly
connected to the relay, and that the relay has been properly configured for
communications (steps described earlier).
The Front Panel settings can now be edited, printed, or changed according to user
specifications. Other setpoint and commands windows can be displayed and edited
in a similar manner. Actual values windows are also available for display. These
windows can be locked, arranged, and resized at will.
Refer to the EnerVista 750/760 Setup Help File for additional information
about the using the software.
http://www.GEmultilin.com
-
Expand the Site List by double
clicking or by selecting the [+] box
Communications Status Indicator
Green = OK, Red = No Comms
750/760
Feeder Management Relay
4–17

Advertisement

Table of Contents
loading

This manual is also suitable for:

760

Table of Contents