REMEHA Quinta Pro 30 Installation And Service Manual page 51

Wall-hung gas condensing boilers
Hide thumbs Also See for Quinta Pro 30:
Table of Contents

Advertisement

Quinta Pro 45 - 65 - 90 - 115
T001507-A
080310 - 123157-AA
CAUTION
Before filling, open the valves on every radiator in the
installation.
In order to be able to read off the water pressure from the
boiler display, the boiler must be switched on.
1. Fill the system with clean tap water (advised water pressure is
between 1.5 and 2 bar).
2. Check the tightness of the water connections.
After switching on the power and if there is adequate water
pressure, the boiler always runs through an automatic
venting program lasting ca. 3 minutes (During filling, air can
escape from the system via the automatic air vent). If the
water pressure is lower than 0.8 bar, the symbol e will
appear. If necessary, top up the water level in the heating
system (recommended hydraulic pressure between 1.5
and 2 bar).
CAUTION
The filling must be carried out within 30 minutes,
4
otherwise the venting program starts and that would
be undesirable if the device is not filled. Switch off the
boiler if the central heating system is not being
topped up immediately.
When venting, prevent water from getting into the
4
jacket and electrical parts of the boiler
4. Installation
49

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Quinta pro 90Quinta pro 115Quinta pro 45Quinta pro 65

Table of Contents