Quinta Pro 45 - 65 - 90 - 115
080310 - 123157-AA
4.5.3.
Install the expansion chamber on the heating return pipe z.
4.5.4.
1. Fit the condensate drain hose and the syphon of the boiler: these
are supplied separately.
2. Mount a synthetic discharge pipe, Ø 32 mm or more, leading to
the mains drainage system.
3. Insert into this the hose of the condensate drain â.
4. Mount a stench trap or a siphon in the discharge pipe.
T002858-A
CAUTION
Do not make a fixed connection owing to maintenance
work on the siphon.
4
4
4
4
4.5.5.
1. Remove the siphon.
2. Fill the siphon with water. This must be completely filled.
3. Re-assemble the siphon.
CAUTION
Fill the water siphon before starting the boiler to avoid
smoke spreading in the room.
T002037-A
Connecting the opened expansion vessel
Connecting the condensate discharge pipe
Do not plug the condensate discharge pipe.
Set the discharge pipe at a gradient of at least 30
mm per metre, maximum horizontal length 5 metres.
Do not drain condensation water into a roof gutter at
any time.
Connect the condensate discharge pipe in
accordance with prevailing standards.
Filling the siphon
4. Installation
23