Pre-Start Inspection - JLG 1230ES Operation And Safety Manual

Vertical mast lift
Table of Contents

Advertisement

SECTION 2 - USER RESPONSIBILITIES, MACHINE PREPARATION AND INSPECTION
2.3

PRE-START INSPECTION

The Pre-Start Inspection should include each of the following:
1. Cleanliness – Check all surfaces for leakage (oil or bat-
tery fluid) or foreign objects. Report any leakage to the
proper maintenance personnel.
2. Structure - Inspect the machine structure for dents,
damage, weld or parent metal cracks or other discrep-
ancies.
.
Parent Metal Crack
2-4
Weld Crack
– JLG Lift –
3. Decals and Placards – Check all for cleanliness and
legibility. Make sure none of the decals and placards
are missing. Make sure all illegible decals and placards
are cleaned or replaced.
4. Operators and Safety Manuals - Check that a copy of
the Operator and Safety Manual is enclosed in the
weather resistant storage container.
5. "Walk-Around" Inspection – Refer to Figure 2-1. on
page 2-6.
6. Battery – Charge as required.
7. Fluid Levels - Check the hydraulic oil level in the
pump reservoir.
8. Accessories/Attachments - Reference the Operator
and Safety Manual of each attachment or accessory
installed upon the machine for specific inspection,
operation, and maintenance instructions.
9. Function Check – Once the "Walk-Around" Inspection
is complete, perform a functional check of all systems
in an area free of overhead and ground level obstruc-
tions. Refer to Section 4 for more specific instructions
on the operation of each function.