3. Tightening of the lug nuts should be done in stages. Fol-
lowing the recommended sequence, tighten lug nuts
per wheel torque.
Table 6-11. Wheel Torque Chart
TORQUE SEQUENCE
1st Stage
20-30 ft lbs
65-80 ft lbs
(28 - 42 Nm)
(91 - 112 Nm)
4. Wheel lug nuts should be torqued after the first 50
hours of operation and after each wheel removal. Check
torque every 3 months or 150 hours of operation.
6-10
2nd Stage
3rd Stage
105 -120 ft lbs
(142 - 163 Nm)
6.1

SUPPLEMENTAL INFORMATION

The following information is provided in accordance with the
requirements of the European Machinery Directive 2006/42/EC
and is only applicable to CE machines.
For electric powered machines, the equivalent continuous A-
Weighted sound pressure level at the work platform is less than
70dB(A).
For combustion engine powered machines, guaranteed Sound
Power Level (LWA) per European Directive 2000/ 14/EC (Noise
Emission in the Environment by Equipment for Use Outdoors)
based on test methods in accordance with Annex III, Part B,
Method 1 and 0 of the directive, is 109 dB.
The vibration total value to which the hand-arm system is sub-
jected does not exceed 2,5 m/s2. The highest root mean square
value of weighted acceleration to which the whole body is sub-
jected does not exceed 0,5 m/s2.