5 SETTINGS
NO.
V1 OR V2
(SOURCE Y)
4
Phase VT and
Auxiliary VT
5
Auxiliary VT
The voltages V1 and V2 will be matched automatically so that the corresponding voltages from the two sources will be
used to measure conditions. A phase to phase voltage will be used if available in both sources; if one or both of the
Sources have only an auxiliary voltage, this voltage will be used. For example, if an auxiliary voltage is programmed to
VAG, the synchrocheck element will automatically select VAG from the other source. If the comparison is required on
a specific voltage, the user can externally connect that specific voltage to auxiliary voltage terminals and then use this
"Auxiliary Voltage" to check the synchronism conditions.
If using a single CT/VT module with both phase voltages and an auxiliary voltage, ensure that only the auxiliary voltage
is programmed in one of the sources to be used for synchrocheck.
Exception: Synchronism cannot be checked between Delta connected phase VTs and a Wye connected auxil-
iary voltage.
NOTE
2.
The relay measures frequency and Volts/Hz from an input on a given source with priorities as established by the con-
figuration of input channels to the source. The relay will use the phase channel of a three-phase set of voltages if pro-
grammed as part of that source. The relay will use the auxiliary voltage channel only if that channel is programmed as
part of the Source and a three-phase set is not.
GE Multilin
V2 OR V1
AUTO-SELECTED
(SOURCE Z)
COMBINATION
SOURCE Y
Auxiliary VT
Phase
Auxiliary VT
Auxiliary
G60 Generator Protection System
5.7 CONTROL ELEMENTS
AUTO-SELECTED VOLTAGE
SOURCE Z
Auxiliary
V auxiliary
(as set for Source z)
Auxiliary
V auxiliary
(as set for selected sources)