Completing A Provisioning Plan - Avaya S8700 Installation Instructions Manual

Installing an avaya s8700 media server with an avaya g650 media gateway
Hide thumbs Also See for S8700:
Table of Contents

Advertisement

Completing a provisioning plan

A provisioning plan should be completed before an installation. The plan determines an appropriate
available port circuit on the media gateway for each telephone, trunk, and peripheral connection needed,
and any auxiliary power for Basic Rate Interface (BRI) and certain display sets.
Obtain copies of the Port Assignment Record forms (or equivalent) from the customer or marketing
representative. See
These forms contain the port assignments and identify the extension numbers (terminal number) of the
telephones. Enter the jack assignments at the equipment room.
The Port Assignment Record should have the following information:
Station or trunk type or feature/service
Building location (floor/room/desk/outlet)
Extension number or trunk group and member number
Port circuit location on the media gateway for each endpoint (media gateway/slot/circuit)
Route from equipment room through site/satellite closets to each endpoint
Auxiliary power supply, if required (main distribution frame (MDF), site/satellite closet, or
information outlet)
166
Figure 65, Port Assignment Record Form,
Installing the Avaya S8700 Media Server with an Avaya G650 Media Gateway
on page 167 for an example of the form.
December 2003

Advertisement

Table of Contents
loading

This manual is also suitable for:

G650

Table of Contents