Avaya S8700 Installation Instructions Manual page 94

Installing an avaya s8700 media server with an avaya g650 media gateway
Hide thumbs Also See for S8700:
Table of Contents

Advertisement

10
Position the media gateway over the holes and adjust the leveling legs until the media gateway is
level.
11
Insert the threaded rods through the media gateway bottom and thread into the concrete floor
anchors.
12
Place a 3/8-inch flat washer onto each rod. Thread a 3/8-16 hex nut onto each rod and tighten
securely.
13
Repeat this procedure for each media gateway to be installed (including the auxiliary cabinet, if
required).
Figure 16: Earthquake mounting — raised computer floor
94
NOTE:
If the media gateways are supplied with cable ductwork, the media gateways must be level
from front to rear and from side to side. They must be square with respect to each other to
within +-1/8-inch (0.3-centimeter).
4 inches
(10.16 cm)
raised
variable
floor
height
concrete
subfloor
Installing the Avaya S8700 Media Server with an Avaya G650 Media Gateway
3/8 inch
flat washer
Nut welded
to frame
Leveling
foot
3/8 - 16
threaded rod
3/8 - 16
Concrete floor
anchor
cab_base CJL 052096
December 2003