Hardware preparation and installation
Before you begin
Refer to the following diagram to determine the required mounting space for the base station,
which is 12 cm (4.7 in) by 20.3 cm (8 in).
Procedure
1. Screw the mounting screws directly into the wall or ceiling, or using the wall anchors
provided. Install the screws 8.3 cm apart vertically, in a space that has 4.5 cm clearance
above the top screw, 6 cm clearance to either side, and 7.5 cm clearance below the bottom
screw.
Leave the screw heads about 2 mm out from the mounting surface.
2. Plug the Ethernet cable into the slot on the back of the base station until you hear it click.
3. Ensure that the cable is securely attached and not disrupted, then mount the base station
on the screws installed in step 1.
April 2020
Installing and Administering D100 SIP Wireless Phones
36