Section 3 • Scheduled Maintenance Procedures
CHECKLIST A PROCEDURES
A-2
Perform Pre-operation
Inspection
Genie requires that this procedure be performed
daily.
Completing a pre-operation inspection is essential
to safe machine operation. The pre-operation
inspection is a visual inspection performed by the
operator prior to each work shift. The inspection is
designed to discover if anything is apparently wrong
with a machine before the operator performs the
function tests. The pre-operation inspection also
serves to determine if routine maintenance
procedures are required.
Complete information to perform this procedure is
available in the appropriate operator's manual. Refer
to the Operator's Manual on your machine.
3 - 8
A-3

Perform Function Tests

Genie requires that this procedure be performed
daily.
Completing the function tests is essential to safe
machine operation. Function tests are designed to
discover any malfunctions before the machine is
put into service. A malfunctioning machine must
never be used. If malfunctions are discovered, the
machine must be tagged and removed from
service.
Complete information to perform this procedure is
available in the appropriate operator's manual. Refer
to the Operator's Manual on your machine.
S-100 • S-105 • S-120 • S-125
June 2011
REV B
Part No. 102916

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

S-100S-125S-120

Table of Contents