Documentation of the inverter
The following must be documented for the inverter:
● The results of the acceptance test.
● The settings of the integrated drive safety functions.
The documentation must be signed.
Who may perform the acceptance test of the inverter?
Personnel from the machine manufacturer, who, on account of their technical qualifications
and knowledge of the safety functions, are in a position to perform the acceptance test in the
correct manner are authorized to perform the acceptance testing of the inverter.
Safety Integrated - SINAMICS G110M, G120, G120C, G120D and SIMATIC ET 200pro FC-2
Function Manual, 04/2014, FW V4.7, A5E34261271B AA
The commissioning tool STARTER logs the settings of the integrated drive functions, if
necessary. See also Section: Documentation for acceptance (Page 309).
5.10 Acceptance tests for the safety functions
Commissioning
157