When lifting manually use your legs, bend your knees, and not your back.
2. Lift the chassis and slide it onto the shelf. Use a mechanical lift or enough people to
safely lift the chassis. A full chassis weighs ~120 kgs an empty chassis weighs ~50
kgs.
Mellanox Technologies

Figure 14: The Rails are Already Connected Onto the Chassis

<40 lbs
40 - 70 lbs
<18 kgs
18 - 32 kgs
Do not use the handles on the fans for lifting or moving the chassis in the rack!
70 - 121 lbs
>121 lbs
32 - 55 kgs
>55 kgs