InfiniBand Switch Platform Hardware User Manual
Push here to release the ejector handle
7
6
1.9.2.2 Inserting a Leaf Board
To insert the leaf board:
1. Check for foreign objects in or mechanical damage to the chassis leaf slots.
2. Check leaf mechanics for any noticeable damage.
3. Check back signal connectors' integrity. Look for any broken signal dividers or any
deviations from the pass criterion shown in Figure 28.
Mellanox Technologies
Figure 27: Leaf Release
9
11
8
10
When hot-swapping any of the units, it is necessary to wait 1 minute after removing
the defective part before inserting the new part. This is necessary so that the manage-
ment module will start a new cycle checking through the leafs and spines for the FW
versions.
Figure 28: Intact vs Defected Signal Connectors
Pass
Pull the ejector handle to remove the leaf
13
15
12
14
17
18
16
Fail
39