1.1.5
Inspecting and Unpacking Each Cabinet
The first task in preparing for installation is inspecting and unpacking the UPS
sections. The UPS sections are shipped bolted to wooden pallets and protected
with outer protective packaging material, as shown in Figure 1---1, and a plastic
inner covering.
Figure 1 ---1. Cabinets as Shipped, with Outer Packaging and Pallet
1.
Carefully inspect the outer packaging for evidence of damage during transit.
CAUTION:
Do not install a damaged cabinet. Report any damage to the carrier and
contact your local sales or service office immediately.
2.
Use a forklift or other material handling equipment to move the cabinet to a
convenient unpacking area. Insert the forklift jacks between the pallet
supports on the bottom of the unit.
CAUTION:
Do not tilt cabinets more than 10 degrees from vertical.
3.
Set each pallet on a firm, level surface, allowing a minimum clearance of
4.6m (15 ft) on each side for removing the cabinets from the pallets.
4.
If outer packaging is secured with steel bands, cut and remove the bands from
around each cabinet.
Powerware 9315 (500 kVA- -750 kVA) Installation and Operation
164201244 REV. D 030101
OUTER
PACKAGING
WOODEN PALLET
1--3
Need help?
Do you have a question about the Uninterruptible Power Supply and is the answer not in the manual?