Powerware 9330 Installation And Operation Manual

Powerware 9330 Installation And Operation Manual

10 kva -- 20 kva 25 kva -- 40 kva
Table of Contents

Advertisement

9
330
Uninterruptible Power
Supply
10 kVA - - 20 kVA
25 kVA - - 40 kVA

Installation and Operation

Manual
164201300 Rev. G

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the 9330 and is the answer not in the manual?

Questions and answers

Summary of Contents for Powerware 9330

  • Page 1: Installation And Operation

    Uninterruptible Power Supply 10 kVA - - 20 kVA 25 kVA - - 40 kVA Installation and Operation Manual 164201300 Rev. G...
  • Page 2: Important Safety Instructions

    ---------------------------------- SAVE THESE INSTRUCTIONS Conserver Ces Instructions concernant la sécurité. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502...
  • Page 3: Table Of Contents

    2.4.4 Installing Options Cabinet External Power Wiring Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 ..........
  • Page 4 ........Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 2---28 .
  • Page 5 Unit Shutdown Screen Reading the Status Indicators Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 ......
  • Page 6 ........Powerware 9330 (10 kVA- -40 kVA) Installation and Operation...
  • Page 7 ..........Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV.
  • Page 8: List Of Figures

    (Powerware 9330 (25 kVA---40 kVA)) Figure 2---4. Removing Rear Shipping Bracket (Powerware 9330 (25 kVA---40 kVA)) Figure 2---5. Battery Cabinet Installation --- Powerware 9330 (10 kVA---20 kVA) (Non–Permanent Mounting) Figure 2---6. Battery Cabinet Installation --- Powerware 9330 (10 kVA---20 kVA) (Permanent Mounting) Figure 2---7.
  • Page 9 Figure 12---7. Events --- History Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 ......
  • Page 10 ......... Powerware 9330 (10 kVA- -40 kVA) Installation and Operation...
  • Page 11: List Of Tables

    Table 12---1. Pin Assignments for Serial Port (DB---9) Table 12---2. Serial Communications Port Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 ....... . .
  • Page 12 This Page Intentionally Left Blank. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502...
  • Page 13: Introduction

    The following illustrations depict a typical Powerware 9330 (10 kVA---20 kVA) UPS System and a typical Powerware 9330 (25 kVA---40 kVA) UPS System...
  • Page 14: System Configurations

    Single Module UPS with integral battery, optional battery cabinet, and optional options cabinet · Single Module UPS with remote battery · Single Module UPS with remote battery and optional options cabinet CABINET OPTIONS CABINET Powerware 9330 (10 kVA- -40 kVA) Installation and Operation BATTERY CABINET 164201300 REV. G 061502...
  • Page 15: Using This Manual

    Chapter 6 -- Understanding UPS Operation -- provides information on understanding UPS operation. · Chapter 7 -- Operational Controls and Features -- describes the standard and optional operational features and controls of the UPS system. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502...
  • Page 16: Conventions Used In This Manual

    In this manual, the term UPS refers only to the UPS cabinet and its internal elements. The term UPS system refers to the entire power protection system—the UPS modules, battery strings and options or accessories installed. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502...
  • Page 17: Safety Considerations

    Battery maintenance or battery replacement should be performed only by authorized service personnel. · Observe all DANGER, CAUTION, and WARNING notices affixed to the inside and outside of the equipment. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 WARNING: xvii...
  • Page 18: For More Information

    System; ; provides procedures for operating the Parallel System, and information about maintenance and responding to system events. Contact your local Powerware Field Service office for information on how to obtain copies of this manual. Getting Help If you need to schedule initial startup, need regional locations and telephone numbers,...
  • Page 19: Section I

    Section I Installation Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502...
  • Page 20 This Page Intentionally Left Blank. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502...
  • Page 21: Getting Started

    The operating environment must meet the weight, airflow, size and clearance, requirements specified in Appendix A. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 1--1...
  • Page 22: Environment Considerations

    For external wiring requirements, including the minimum AWG size of external wiring, refer to Tables A through F in Appendix A for the Powerware 9330 (10 kVA---20 kVA) UPS or Tables G through M in Appendix A for the Powerware 9330 (25 kVA---40 kVA) UPS.
  • Page 23: Inspecting And Unpacking Each Cabinet

    Figures 1---1 or 1---2, and protected with outer protective packaging material. Figure 1 ---1. Powerware 9330 (10 kVA ---20 kVA) UPS Cabinet as Shipped on Pallet Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502...
  • Page 24 Figure 1 ---2. Powerware 9330 (25 kVA ---40 kVA) UPS Cabinet as Shipped on Pallet Carefully inspect the outer packaging for evidence of damage during transit. CAUTION: Do not install a damaged cabinet. Report any damage to the carrier and contact your local sales or service office immediately.
  • Page 25 After removing the protective covering, inspect the contents for any evidence of physical damage, and compare each item with the Bill of Lading. If damage has occurred or shortages are evident, contact the Powerware, Inc. Customer Service Department immediately to determine the extent of the damage and its impact upon further installation.
  • Page 26 This Page Intentionally Left Blank. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 1--6 164201300 REV. G 061502...
  • Page 27: Installing The Ups System

    Details about control wiring are provided in each procedure for connecting options and features. Drawing 164201300---2 and Tables X and Y in Appendix A identify the control wiring terminations. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 WARNING: 10˚...
  • Page 28: Ups Cabinet Installation

    Slowly roll the cabinet toward the rear of the pallet. Once the pallet tilts, continue rolling the cabinet down the pallet until the cabinet is clear of the pallet. 2--2 Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502...
  • Page 29 PALLET Figure 2 ---1. Removing Front Shipping Bracket (Powerware 9330 (10 kVA ---20 kVA)) Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 SOLID FRONT PANEL FRONT SHIPPING BRACKET (3) FRONT VIEW VENTED FRONT PANEL SHIPPING...
  • Page 30 PALLET REAR SHIPPING BRACKET (3) Figure 2 ---2. Removing Rear Shipping Bracket (Powerware 9330 (10 kVA ---20 kVA)) 2--4 SKID BOLTS (4) (3 PLACES) SHIPPING BOLTS (1) SHIPPING BOLTS (2) REAR VIEW Powerware 9330 (10 kVA- -40 kVA) Installation and Operation...
  • Page 31: Unloading The Powerware 9330 (25 Kva

    (see Figure 2---3). If the leveling feet are not fully retracted, turn the leveling feet until they are retracted. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 2--5...
  • Page 32 PALLET SOLID FRONT PANEL Figure 2 ---3. Removing Front Shipping Bracket (Powerware 9330 (25 kVA ---40 kVA)) 2--6 FRONT SHIPPING SHIPPING BOLTS (1) BRACKET (3) FRONT VIEW Powerware 9330 (10 kVA- -40 kVA) Installation and Operation VENTED FRONT PANELS SHIPPING BOLTS (2) 164201300 REV.
  • Page 33 PALLET REAR SHIPPING BRACKET (3) Figure 2 ---4. Removing Rear Shipping Bracket (Powerware 9330 (25 kVA ---40 kVA)) Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 SKID BOLTS (4) (4 PLACES) SHIPPING BOLTS (1) SHIPPING...
  • Page 34 2.3 and 2.4; otherwise, proceed to step 18. Secure cabinet to floor with contractor supplied hardware and proceed to paragraph 2.2.5. 2--8 Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502...
  • Page 35: Installing Optional Remote Battery Power Wiring To The Powerware 9330 (10 Kva

    Refer to Chapter 15 “Specifications”, for maximum battery charger currents. If not already removed, remove left front solid panel and right front vented panel from the Powerware 9330 (10 kVA---20 kVA) UPS cabinet . Front panels are secured with magnetic latches and are removed by pulling panels straight forward to disengage magnetic latches (see Figure 2---1).
  • Page 36: Installing Optional Remote Battery Power Wiring To The Powerware 9330 (25 Kva

    Refer to Chapter 15 “Specifications”, for maximum battery charger currents. If not already removed, remove left front solid panel, and front vented panels from the Powerware 9330 (25 kVA---40 kVA) UPS cabinet . Front panels are secured with magnetic latches and are removed by pulling panels straight forward to disengage magnetic latches (see Figure 2---3).
  • Page 37: Installing Ups External Power Wiring

    Installing UPS External Power Wiring Remove left front solid panel and right front vented panel from the Powerware 9330 (10 kVA---20 kVA) UPS cabinet or left front solid panel and front vented panels from the Powerware 9330 (25 kVA---40 kVA) UPS cabinet. Front panels are secured with magnetic latches and are removed by pulling panels straight forward to disengage magnetic latches (see Figure 2---1 or 2---3).
  • Page 38: Installing Customer Connections

    Reinstall Customer Interface conduit landing plate. Refer to Chapter 4 for installation instructions. When wiring is complete, secure UPS by reinstalling all panels removed in previous steps. 2--12 Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502...
  • Page 39: Battery Cabinet Installation

    Roll the Battery cabinet to a spot near the right side of the UPS. Remove left front solid panel, and right front vented panel from the Powerware 9330 (10 kVA---20 kVA) UPS cabinet or left front solid panel and front vented panels from Powerware 9330 (25 kVA---40 kVA) UPS cabinet. Front panels are secured with magnetic latches and are removed by pulling panels straight forward to disengage magnetic latches (see Figure 2---1 or 2---3).
  • Page 40 BATTERY CONNECTOR Figure 2 ---5. Battery Cabinet Installation --- Powerware 9330 (10 kVA ---20 kVA) (Non–Permanent Mounting) Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 2--14 164201300 REV. G 061502...
  • Page 41 BATTERY CONNECTOR Figure 2 ---6. Battery Cabinet Installation --- Powerware 9330 (10 kVA ---20 kVA) Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 (Permanent Mounting) 2--15...
  • Page 42 BATTERY CONNECTOR Figure 2 ---7. Battery Cabinet Installation --- Powerware 9330 (25 kVA ---40 kVA) (Non–Permanent Mounting) Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 2--16 164201300 REV. G 061502...
  • Page 43 BATTERY CONNECTOR Figure 2 ---8. Battery Cabinet Installation --- Powerware 9330 (25 kVA ---40 kVA) Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 (Permanent Mounting) 2--17...
  • Page 44: Joining Additional Battery Cabinets

    To join additional battery cabinets, perform the following steps. Refer to Figure 2---5 for non-permanent installation or Figure 2---6 for permanent installation of the Powerware 9330 (10 kVA---20 kVA) UPS and Figure 2---7 for non-permanent installation or Figure 2---8 for permanent installation of the Powerware 9330 (25 kVA---40 kVA) UPS.
  • Page 45 When all wiring is complete, proceed to Chapter 3 and connect battery strings in accordance with instructions contained in paragraph 3.4.2. Repeat steps 1 through 21 to join additional Battery cabinets. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 2--19...
  • Page 46: Options Cabinet Installation

    Roll the Options cabinet to a spot near the left side of the UPS. Remove left front solid panel, and right front vented panel from the Powerware 9330 (10 kVA---20 kVA) UPS cabinet or left front solid panel and front vented panels from Powerware 9330 (25 kVA---40 kVA) UPS cabinet. Front panels are secured with magnetic latches and are removed by pulling panels straight forward to disengage magnetic latches (see Figure 2---1 or 2---3).
  • Page 47 Figure 2 ---9. Options Cabinet Installation --- Powerware 9330 (10 kVA ---20 kVA) (Non–Permanent Mounting) Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 2--21 164201300 REV. G 061502...
  • Page 48 Figure 2 ---10. Options Cabinet Installation --- Powerware 9330 (10 kVA ---20 kVA) (Permanent Mounting) Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 2--22 164201300 REV. G 061502...
  • Page 49 Figure 2 ---11. Options Cabinet Installation --- Powerware 9330 (25 kVA ---40 kVA) (Non–Permanent Mounting) Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 2--23 164201300 REV. G 061502...
  • Page 50 Figure 2 ---12. Options Cabinet Installation --- Powerware 9330 (25 kVA ---40 kVA) (Permanent Mounting) Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 2--24 164201300 REV. G 061502...
  • Page 51 Secure the back of Options cabinet to the back of the UPS cabinet with the tie/grounding bracket. Secure the bracket with the side panel mounting screws. Secure cabinets to floor with contractor supplied hardware. Proceed to paragraph 2.4.3. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 2--25...
  • Page 52: Installing Options Cabinet Internal Power Wiring

    Installing Options Cabinet Internal Power Wiring Remove left front solid panel, and right front vented panel from the Powerware 9330 (10 kVA---20 kVA) UPS cabinet or left front solid panel and front vented panels from Powerware 9330 (25 kVA---40 kVA) UPS cabinet. Front panels are secured with magnetic latches and are removed by pulling panels straight forward to disengage magnetic latches (see Figure 2---1).
  • Page 53: Installing Options Cabinet External Power Wiring

    Options cabinet. Refer to Appendix A of this manual for wiring and termination requirements and wiring access information. Note wiring connections for dual feed systems. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 2--27...
  • Page 54: Initial Startup

    Installation Checklist to be sure you have completed all applicable equipment installation. NOTE: The Installation Checklist MUST be completed prior to starting the UPS system for the first time. 2--28 Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502...
  • Page 55: Installation Checklist

    UPS cabinet. Summary alarms and/or building alarms are wired appropriately. (OPTIONAL) Startup and operational checks performed by authorized service personnel. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 2--29...
  • Page 56 Notes ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 2--30 164201300 REV. G 061502...
  • Page 57: Installing And Connecting Batteries

    Suivre les précautions qui s’imposent. · Pour le remplacement, utiliser le même nombre et modéle des batteries. · L’élimination des batteries est règlementée. Consulter les codes locaux à cet effet. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 3--1...
  • Page 58: Battery Type

    Ensure that battery breaker CB2 is in the OFF position. If not, set breaker to OFF position. Remove left front solid panel and right front vented panel from Powerware 9330 (10 kVA---20 kVA) UPS or left front solid panel and front vented panels from Powerware 9330 (25 kVA---40 kVA) UPS.
  • Page 59 Figure 3 ---1. Battery Schematic --- Powerware 9330 (10 kVA ---20 kVA) UPS and Battery Cabinet Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 3--3 164201300 REV. G 061502...
  • Page 60 Figure 3 ---2. Battery Schematic --- Powerware 9330 (25 kVA ---40 kVA) UPS Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 3--4 164201300 REV. G 061502...
  • Page 61: Installing Internal Batteries In The Battery Cabinet

    Ensure that battery breaker CB2 is in the OFF position. If not, set breaker to OFF position. Remove left front solid panel and right front vented panel from Powerware 9330 (10 kVA---20 kVA) UPS or left front solid panel and front vented panels from Powerware 9330 (25 kVA---40 kVA) UPS.
  • Page 62: Electrically Connecting Battery Cabinet Battery Strings

    Secure the Battery Cabinet by reinstalling safety shield panel, and front vented panel. If you are installing more than one battery cabinet, perform Steps 1 through 6 for each cabinet. 3--6 WARNING: THIS SECTION. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502...
  • Page 63 CONNECT RED TO BLACK Figure 3 ---3. Battery String Connection Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 BATTERY STRINGS CONNECT RED TO BLACK BLACK CONNECTOR CONNECT RED TO BLACK CONNECTOR 3--7...
  • Page 64: Installing And Connecting Remote Battery System

    Install battery system in accordance with battery and rack manufactures instructions. Install DC disconnect device between battery system and UPS Cabinet. Connect battery system to UPS cabinets (refer to Paragraph 2.2.3 or 2.2.4). 3--8 Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502...
  • Page 65: Installation Procedures

    Securely mount the Remote EPO switch enclosure bottom. Recommended locations include operator’s consoles or by exit doors. Refer to Appendix A, Drawing 164201300---18, for enclosure dimensions and wiring knockouts. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 Figure 4 ---1. Remote EPO Control...
  • Page 66 Connect the Remote EPO wiring as shown in Tables 4---1 and 4---2 and Figure 4---2. If you are installing multiple Remote EPO stations, wire additional stations in series with the first Remote EPO. 4--2 COVER BOTTOM ENCLOSURE Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502...
  • Page 67 Turn cover over and secure to enclosure bottom. Secure the UPS by reversing all steps taken to prepare it for Remote EPO installation. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 To Communications Server...
  • Page 68 This Page Intentionally Left Blank. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 4--4 164201300 REV. G 061502...
  • Page 69: Installing A Remote Monitor Panel

    Figure 5---1 shows an RMP . Drawing 164201300---19 in Appendix A shows the enclosure dimensions and cable exit openings. Figure 5 ---1. Remote Monitor Panel (RMP) Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 HORN SILENCE BUTTON...
  • Page 70: To Install An Rmp

    Table 5---1. RMP Wire Terminations To UPS Remote Monitor Card J1---1 J1---3 J1---4 J1---5 J1---6 Powerware 9330 (10 kVA- -40 kVA) Installation and Operation Remarks Use Belden 8690 060 B ld 8690 060 or equivalent Cable or equivalent Cable 164201300 REV. G 061502...
  • Page 71 BETWEEN THE REMOTE MONITOR AND THE UPS IS NOT TO EXCEED 500 FEET. Figure 5 ---3. Remote Monitor Panel (RMP) --- Top Internal View Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 PLUG-IN TERMINAL BLOCK J1 TO REMOTE MONITOR Figure 5 ---2.
  • Page 72 This Page Intentionally Left Blank. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 5--4 164201300 REV. G 061502...
  • Page 73: Section Ii

    Section II Operation Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502...
  • Page 74 This Page Intentionally Left Blank. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502...
  • Page 75: Understanding Ups Operation

    Operation Looking Inside the UPS System The Powerware 9330 is a continuous duty, solid-state, transformerless (at 208 VAC), three phase, true online system that provide conditioned and uninterruptible AC power to the UPS systems output. The UPS supports process control, data processing, telecommunications/PBX, research, and non---patient medical equipment.
  • Page 76 DC- -DC BOOST INVERTER RECTIFIER CONVERTER POWER PROCESSING UNIT DIGITAL METERING MAINTENANCE BYPASS SWITCH STATIC SWITCH BACKFEED PROTECTION CONTACTOR Powerware 9330 (10 kVA- -40 kVA) Installation and Operation OUTPUT CONTACTOR OUTPUT FILTER AC OUTPUT TO CRITICAL LOAD 164201300 REV. G 061502...
  • Page 77: Ups Modes

    System events, alarm horns, and indicator lights are described in Chapter 11, “Responding to System Events.” The following descriptions provide the differences in UPS operating modes. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 6--3...
  • Page 78: Normal Mode

    6--4 NORMAL MODE STATIC SWITCH BOOST CONVERTER CHARGER BATTERY Powerware 9330 (10 kVA- -40 kVA) Installation and Operation INVERTER MAINTENANCE BYPASS SWITCH Main Power Flow Trickle Current Energized De- -Energized 164201300 REV. G 061502...
  • Page 79 If the UPS suffers an internal failure, it switches automatically to Bypass mode and remains in that mode until the failure is corrected and the UPS is back in service. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502...
  • Page 80: Bypass Mode

    6--6 BYPASS MODE STATIC SWITCH BOOST CONVERTER CHARGER BATTERY Powerware 9330 (10 kVA- -40 kVA) Installation and Operation INVERTER MAINTENANCE BYPASS SWITCH Main Power Flow Trickle Current Energized De- -Energized 164201300 REV. G 061502...
  • Page 81 Bypass mode is a normal operating mode, and not an alarm condition. However, if the UPS is unable to return to Normal mode following an automatic transfer to Bypass mode, an alarm condition is recorded. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 6--7...
  • Page 82: High Efficiency Mode

    While the UPS is in High Efficiency mode, the NORMAL light on the front display will illuminate. 6--8 STATIC SWITCH BOOST CONVERTER CHARGER BATTERY Powerware 9330 (10 kVA- -40 kVA) Installation and Operation INVERTER MAINTENANCE BYPASS SWITCH Main Power Flow Trickle Current Energized De- -Energized 164201300 REV. G 061502...
  • Page 83: Battery Mode

    The UPS will remain in this operating mode until the input power to the rectifier is again within the specified voltage or frequency acceptance windows. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 BATTERY MODE...
  • Page 84 The greater the load, the less support time the battery will have. Decrease the load, and the battery support time will generally increase. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 6--10 164201300 REV. G 061502...
  • Page 85: Test Mode

    MAINTENANCE BYPASS SWITCH RECTIFIER Breakers Contactors Closed Open Figure 6 ---6. Path of Current Through the UPS in Test Mode Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 TEST MODE STATIC SWITCH BOOST CONVERTER CHARGER...
  • Page 86: Maintenance Bypass Mode

    DC IN Bus prior to the input contactor being closed. 6--12 STATIC SWITCH BOOST CONVERTER CHARGER BATTERY Powerware 9330 (10 kVA- -40 kVA) Installation and Operation INVERTER MAINTENANCE BYPASS SWITCH Main Power Flow Trickle Current Energized De- -Energized 164201300 REV. G 061502...
  • Page 87: Boost Converter And Neutral Regulator

    External Batteries connect in parallel to the Internal Battery via an internal breaker. The internal charger charges the Batteries in parallel or in conjunction with an optional external charger Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 6--13...
  • Page 88 This Page Intentionally Left Blank. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 6--14 164201300 REV. G 061502...
  • Page 89: Operational Controls And Features

    Figure 7---1 identifies and shows the location of the controls and indicators on the Powerware 9330 (10 kVA---20 kVA) UPS and Figure 7---2 identifies and shows the location of the controls and indicators on the Powerware 9330 (25 kVA---40 kVA) UPS.
  • Page 90 AC OUTPUT AC INPUT BREAKER BREAKER OPTIONS CABINET MAINTENANCE BYPASS SWITCH OPTIONS CABINET Figure 7 ---1. Powerware 9330 (10 kVA ---20 kVA) UPS Controls and Indicators 7--2 COLD BYPASS START BATTERY BREAKER SWITCH BREAKER CB2 AC INPUT BREAKER CB1 MAINTENANCE...
  • Page 91 BREAKER BREAKER OPTIONS CABINET MAINTENANCE BYPASS SWITCH OPTIONS CABINET Figure 7 ---2. Powerware 9330 (25 kVA ---40 kVA) UPS Controls and Indicators Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 COLD AC INPUT CONTROL START...
  • Page 92: Ups Circuit Breakers

    The UPS uses these inputs to monitor your building alarms in addition to the UPS status. This feature is described further in Chapter 10, “Using Features and Options.” 7--4 Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502...
  • Page 93: Advanced Battery Management

    UPS output. The operation of the REMOTE EMERGENCY POWER OFF pushbutton is described in detail in Chapter 9, “UPS Operating Instructions.” Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 7--5...
  • Page 94: Remote Monitor Panel

    The Parallel Cabinet allows the creation of a system that allows two to four UPMs to operate in parallel capacity or redundancy to provide more capacity than a single UPM and as backup for each other. 7--6 Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502...
  • Page 95: Communications

    · Single RS---232 port · Multiple RS---232 ports · AS---400 interface · SNMP adapter · Modem driver · Web enabled SNMP adapter · Mod Bus driver. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 7--7...
  • Page 96: Safety Considerations

    Observe all DANGER, CAUTION, and WARNING notices affixed to the inside and outside of the equipment. · Always conform to the more detailed safety precautions described in “Important Safety Instructions” section of Chapter 14. 7--8 Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502...
  • Page 97: Symbols, Controls, And Indicators

    Stop and refer to the Operator’s Manual for more information. RISK OF ELECTRIC SHOCK There is a risk of electric shock present, and you should observe associated warnings. The UPS contains high voltages. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 7--9...
  • Page 98 This Page Intentionally Left Blank. 7--10 Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502...
  • Page 99: Using The Control Panel

    UPS Control Panel to monitor the UPS. Refer to Chapter 9 UPS Operating Instructions for use of the operational controls. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 Figure 8 ---1. UPS Control Panel...
  • Page 100: Using The Lcd Screen And Pushbuttons

    After approximately one hour, the display screen dims. To restore the screen, press any pushbutton once. 8--2 STSW METERS CONTROLS Alarm Powerware 9330 (10 kVA- -40 kVA) Installation and Operation OUTPUT SETUP , depress the respective 164201300 REV. G 061502...
  • Page 101: Using The Main Menu

    01/10/2001 BATT EVENTS METERS Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 Displays the list of Active System Events and a historical log of system events. Displays performance meters for the system or critical load.
  • Page 102: System Event Screens

    Figure 8 ---5. Active System Events Screen 8--4 HISTORY 12/15/2000 EVENTS ACTIVE EVENTS AC INPUT UNDERVOLTAGE BYPASS UNDER VOLTAGE HISTORY Powerware 9330 (10 kVA- -40 kVA) Installation and Operation pushbuttons from the display menu. 10:20:03.539 pushbuttons from the display menu. 164201300 REV. G 061502...
  • Page 103: System Meter Screens

    The Output screen shows the phase-to-neutral voltage, phase current, and frequency, being supplied by the UPS, followed by the KVA, KW, and power factor measurements. Figure 8 ---7. Output Meter Screen Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 INPUT FREQ Figure 8 ---6.
  • Page 104 The Battery screen displays the DC voltage (V), the DC current (I), and of battery time remaining TIME REMAINING --- 8--6 BYPASS Freq Figure 8 ---8. Bypass Meter Screen BATTERY MINUTES Figure 8 ---9. Battery Meter Screen Powerware 9330 (10 kVA- -40 kVA) Installation and Operation the minutes 164201300 REV. G 061502...
  • Page 105 The Output Current Screen displays a real-time bar graph of the output current of the UPS. The graph shows the current for each phase. Output I 125% 100% Figure 8 ---10. Output Current (Load) Meter Screen Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 8--7...
  • Page 106: System Setup

    Figure 8 ---12. Contrast Adjust Menu Screen 8--8 SYSTEM SETUP CONTRAST DATE & TIME SERIAL PORTS VERSIONS Figure 8 ---11. Setup Menu Screen CONTRAST ADJUST Powerware 9330 (10 kVA- -40 kVA) Installation and Operation SELECT pushbutton. 164201300 REV. G 061502...
  • Page 107 To complete the save function and return to the Setup Menu screen, select the pushbutton. DAY DT MONTH YEAR HOUR MINUTE SAVE Figure 8 ---13. Date & Time Screen Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 DATE & TIME 2000...
  • Page 108: Serial Ports

    To complete the save function and return to the Setup Menu screen, select the pushbutton. PORT BAUD COM1 9600 8--10 SERIAL PORTS PARITY DATA NONE Figure 8 ---14. Port Setup Screen Powerware 9330 (10 kVA- -40 kVA) Installation and Operation pushbuttons to select YES STOP SAVE 164201300 REV. G 061502...
  • Page 109 Figure 8---15 shows the Versions screen. To return to the System Setup menu screen, select the INVERTER MACHINE CONTROL COMM SERVER DISPLAY Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 pushbutton. VERSIONS 1.04 1.06 1.08 1.02...
  • Page 110: System Controls Screen

    Figure 8 ---16. System Controls Screen in Normal Mode 8--12 SYSTEM CONTROLS ONLINE NORMAL MODE REQUESTED BYPASS CHARGER Powerware 9330 (10 kVA- -40 kVA) Installation and Operation PPU ON TOGGLES BETWEEN ONLINE AND HI-EFF, DEPENDING ON MODE 164201300 REV. G 061502...
  • Page 111: System Controls

    NORMAL BYPASS TOGGLES BETWEEN NORMAL AND HI-EFF, DEPENDING ON MODE Figure 8 ---17. System Controls Screen in High Efficiency Mode Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 SYSTEM CONTROLS HI-EFF CHARGER PPU ON TOGGLES BETWEEN...
  • Page 112: Charger Controls Screen

    Controls screen. Use the controls on this screen to turn the battery charger on and off. Figure 8---18 shows the Charger Controls screen. CHARGER CONTROLS CHARGER ON CHARGER OFF Figure 8 ---18. Charger Controls Screen Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 8--14 164201300 REV. G 061502...
  • Page 113: Unit Shutdown Screen

    Chapter 9, “UPS Operating Instructions”. THIS WILL REMOVE POWER TO THE LOAD! HOLD YES FOR 2 SECONDS TO POWER DOWN Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 UNIT SHUTDOWN ARE YOU SURE? Figure 8 ---19.
  • Page 114: Reading The Status Indicators

    All alarms are accompanied by an audible horn. To silence the horn, press the Alarm Off pushbutton switch. The Alarm indicator may be lit along with other indicators. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502...
  • Page 115: Starting The Ups In Normal Mode

    UPS transfers to Normal mode. The status indicator on the UPS Control Panel indicates the UPS is in Bypass mode. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 OPEN...
  • Page 116: Starting The Ups In Bypass Mode

    The critical load is immediately supplied by the bypass source, in Bypass mode. The UPS is now operating in the bypass mode and the BYPASS status indicator is illuminated. 9--2 OPEN OPEN Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502...
  • Page 117: Starting The Power Processing Unit

    Normal mode and supply the critical load. The UPS is now operating in the Bypass mode and the BYPASS status indicator is illuminated. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 OPEN...
  • Page 118: Cold Starting The Ups

    Select NORMAL or HI -- EFF from the System Control menu. Normal Mode Requested appears on the screen. The status indicator on the UPS Control Panel indicates the UPS is in Normal---Battery mode. 9--4 OPEN OPEN Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502...
  • Page 119: Transfer From Normal To Bypass Mode

    The PPU status indicates READY. System is now on bypass and UPS power processor remains on. WARNING: Power is present inside the UPS and Options cabinets. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 9--5...
  • Page 120: Transfer From Normal To High Efficiency Mode

    The UPS is now operating in the Normal mode and the NORMAL status indicator is illuminated. The PPU status indicates ONLINE. 9--6 Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502...
  • Page 121: Ups And Critical Load Shutdown

    The maintenance bypass source supplies the critical load. WARNING: Power is present inside the UPS and Options cabinets Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 The input, output, and battery contactors the upstream input feeder...
  • Page 122: Options Cabinet Maintenance Bypass Transfer

    Do not attempt to restart the system after Load Off until the cause of the shutdown has been identified and cleared. To restart the UPS after pressing the LOAD OFF pushbutton, follow the procedure, in paragraphs 9.2 or 9.3. 9--8 Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502...
  • Page 123: To Use The Repo Switch

    NOTE: The following instructions are for the Powerware supplied REPO switch. If a customer supplied REPO switch is used it may not activate in the same manner.
  • Page 124 This Page Intentionally Left Blank. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 9--10 164201300 REV. G 061502...
  • Page 125: General Purpose Relay Contacts

    UPS. This feature is useful if the UPS is located in a remote area where the UPS alarm horn may not be heard immediately. CAUTION: Contacts should not be operated in excess of 120 VAC @ 5A maximum. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 10--1...
  • Page 126: Optional Remote Monitor Panel

    You can surface-mount an RMP on a desktop, secure to a wall, or place in another convenient location. Figure 10---1 shows an RMP . HORN SILENCE Figure 10 ---1. Remote Monitor Panel Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 10--2 164201300 REV. G 061502...
  • Page 127 The NORMAL indicator is also lit. After 30 seconds of run time, the alarm indicator will illuminate and a horn sound. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 10--3...
  • Page 128 This Page Intentionally Left Blank. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 10--4 164201300 REV. G 061502...
  • Page 129: Responding To System Events

    (For descriptions of the status indicators, refer to paragraph 8.6 “Reading the Status Indicators” of Chapter 8.) Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 11--1...
  • Page 130: System Event Messages

    HA User Action Required HA Condition Cleared HA Service Required HA Condition Cleared HA Service Required HA Condition Cleared HA Service Required HA Condition Cleared Powerware 9330 (10 kVA- -40 kVA) Installation and Operation Indication Service Required 164201300 REV. G 061502...
  • Page 131 Gate Driver Failed 1 Gate Driver Failed 1 OK Heat Sink Thermistor Failure Heat Sink Thermistor Failure OK Input Failure Input Failure OK Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 Horn Phone Relay HA Service Required...
  • Page 132 HA Service Required HA Condition Cleared HA User Action Required HA Condition Cleared HA Service Required HA Condition Cleared Powerware 9330 (10 kVA- -40 kVA) Installation and Operation Indication Service Required User Action Required Service Required Condition Cleared 164201300 REV. G 061502...
  • Page 133 Warning: Battery Time is Low OK Table Key To Log Column HA --- Event recorded in History and Active Logs. --- Event recorded in Active Log only. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 Horn Phone...
  • Page 134 HA Information Only HA Condition Cleared HA Information Only HA Condition Cleared HA Information Only HA Condition Cleared HA Information Only HA Condition Cleared Powerware 9330 (10 kVA- -40 kVA) Installation and Operation Indication Protection Level Information Only 164201300 REV. G 061502...
  • Page 135 Phone #1 Failed Phone #2 Failed Phone #3 Failed Phone #4 Failed SBM IO 1 Not Reporting SBM IO Not Reporting OK Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 Horn Phone Relay HA Information Only...
  • Page 136 HA --- Event recorded in History and Active Logs. --- Event recorded in Active Log only. 11--8 Horn Phone Relay Powerware 9330 (10 kVA- -40 kVA) Installation and Operation Indication Information Only Condition Cleared Information Only Condition Cleared Information Only...
  • Page 137 UPS Power Supply OK Table Key To Log Column HA --- Event recorded in History and Active Logs. --- Event recorded in Active Log only. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 Horn Phone Relay Log...
  • Page 138 Table Key To Log Column HA --- Event recorded in History and Active Logs. --- Event recorded in Active Log only. 11--10 Horn Phone Relay Log Powerware 9330 (10 kVA- -40 kVA) Installation and Operation Indication 164201300 REV. G 061502...
  • Page 139: Connecting Equipment To A Serial Port

    Communications 12.1 Description This chapter describes the serial communications feature of the Powerware 10 kVA---20 kVA and 25 kVA---40 kVA UPS. One serial communications port on the UPS allows you to connect equipment to view system event information. The following sections describe the serial communications feature, and provide information about connecting hardware, and using terminal mode.
  • Page 140: Configuring The Serial Ports

    Input to UPS Receive Data Output from UPS Data Set Ready Return Data Terminal Ready Clear to Send Ready to Send Stop Bit Powerware 9330 (10 kVA- -40 kVA) Installation and Operation NOT USED Comments Parity Handshaking Disabled 164201300 REV. G 061502...
  • Page 141: Display Ups Control Panel

    Chapter 8 “Using the Control Panel” for instructions on navigating the control panel. Figures 12---2 through 12---17 show the typical screens using this function. Figure 12 ---2. Main Screen --- UPS Normal Mimic Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 12--3...
  • Page 142 Figure 12 ---3. Main Screen --- UPS On Battery Mimic Figure 12 ---4. Main Screen --- UPS On Bypass Mimic Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 12--4 164201300 REV. G 061502...
  • Page 143 Figure 12 ---5. System Controls Figure 12 ---6. Load Off Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 12--5 164201300 REV. G 061502...
  • Page 144 Figure 12 ---7. Events --- History Figure 12 ---8. Events --- Active Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 12--6 164201300 REV. G 061502...
  • Page 145 Figure 12 ---9. Input Meter Figure 12 ---10. Output Meter Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 12--7 164201300 REV. G 061502...
  • Page 146: Figure 12

    Figure 12 ---11. Bypass Meter Figure 12 ---12. Output Current (Load) Meter Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 12--8 164201300 REV. G 061502...
  • Page 147: Figure 12

    Figure 12 ---13. Setup Figure 12 ---14. Contrast Adjust Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 12--9 164201300 REV. G 061502...
  • Page 148: Figure 12

    Figure 12 ---15. Date and Time Setup Figure 12 ---16. Serial Port Setup Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 12--10 164201300 REV. G 061502...
  • Page 149: Figure 12

    Figure 12 ---17. Versions Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 12--11 164201300 REV. G 061502...
  • Page 150: Event History Log

    Second (2 digits) Hundredths of Second (2 digits) Keyword (ALARM, NOTICE, COMMAND, or STATUS) System Diagnostic Information Carriage Return Character (ASCII 13) Line Feed (ASCII 10) Powerware 9330 (10 kVA- -40 kVA) Installation and Operation <CR> <LF> :::: 164201300 REV. G 061502...
  • Page 151: Figure 12

    08/12/2000 14:17:20.900 NOTICE: Input Under Voltage OK 08/12/2000 14:17:23.606 ALARM: Rectifier Under Voltage OK 08/12/2000 14:17:25.557 ALARM: Battery Under Voltage OK 08/12/2000 14:19:01.899 CMD: 08/12/2000 14:19:04.089 STATUS: K1 (Input) Closed Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 0.97 0.98 0.96...
  • Page 152 This Page Intentionally Left Blank. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 12--14 164201300 REV. G 061502...
  • Page 153: Remote Notification

    Numeric paging support allows the UPS to call a paging service and send numeric messages. The Housekeeping function maintains the link between the UPS and modem. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 13--1...
  • Page 154: Remote Notification Features

    Remote and local ability to clear Call Out alarms and events. · Error detection and correction for misconfigured and disconnected modems. · Uses standard modems and null modem cables available at your local computer supply center. 13--2 Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502...
  • Page 155: Description Of Operation

    “ATDS=0”, “ATDS=1” for group two, “ATDS=2” for group three, and “ATDS=3” for group four,. This allows the user to program the desired phone numbers into the modem. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 13--3...
  • Page 156 (or the modem is successfully re-initialized). For each unsuccessful attempt, the UPS logs a check modem event into the event log. When the modem link is confirmed, the UPS communications resume normal operation. 13--4 Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502...
  • Page 157: Hardware Requirements

    2 pin 3 pin 4 pin 5 pin 6 pin 7 pin 8, 20 Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 Male DB9 pin 2 pin 3 pin 8 pin 7 pin 1, 4...
  • Page 158: Configuring The Modem To Call A Remote Computer

    5. To program a group two number, key in [A], [T], [&], [Z], [1], [=], [xxxxxxx], then press [ENTER]. 6. To program a group three number, key in [A], [T], [&], [Z], [2], [=], [xxxxxxx], then press [ENTER]. 13--6 Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502...
  • Page 159: Configuring The Modem To Call A Numeric Pager

    6. To program a group three number, key in [A], [T], [&], [Z], [2], [=], [xxxxxxx], [,], [,], [,], [yyyyyyy], [#], then press [ENTER]. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 Keying in the “#”...
  • Page 160: Ups Setup Configuration

    (refer to Chapter 12, “Serial Communications”). If using a standard serial cable, a null modem adapter is required for the connection to the modem. The Powerware 9330 UPS can only use the DB---9 serial Port for the Remote Notification option. This connection is located on the back of the UPS cabinet.
  • Page 161: Default Events

    Check K5 Check Neutral Regulator DC Link Voltage Sensing Failure Heat Sink Thermistor Failure Input Failure UPS Tripped Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 Action Notify Service Notify Service Notify Service Notify Service...
  • Page 162 This Page Intentionally Left Blank. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 13--10 164201300 REV. G 061502...
  • Page 163: Maintaining The Ups System

    If the string requires service, refer to the battery manufacturer’s operating manual for instructions on battery maintenance, or contact your local field service office. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 14--1...
  • Page 164 Suivre les précautions qui s’imposent. · Pour le remplacement, utiliser le même nombre et modéle des batteries. · L’élimination des batteries est règlementée. Consulter les codes locaux à cet effet. 14--2 Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502...
  • Page 165: Performing Preventive Maintenance

    Monitor system parameters as described in Chapter 8, “Using the Control Panel.” The UPS cooling air intake filter on the Powerware 9330 (10 kVA---20kVA) is located behind the removable front panel. The UPS cooling air intake filters on the Powerware 9330 (25 kVA---40kVA) are located behind both removable front panels.
  • Page 166: Maintenance Training

    For more information about training and other services, contact the Powerware Corporation Training Coordinator in Raleigh, North Carolina, or call Powerware corporation field service at 1 -- 800 -- 843 -- 9433. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 14--4 164201300 REV.
  • Page 167: Product Specifications

    Input Current Harmonic Content Power Factor Line Surges Battery Voltage Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 Models 10, 15, 20 kVA 25, 30, 35, 40 kVA 600 VAC for operation from 510 VAC to 660 VAC (50/60 Hz)
  • Page 168: Ups System Output

    0.5 Hz 1 Hz per second maximum (adjustable) 1101---110% for 10 minutes 1111---125% for 1 minute 300% peak for 10 cycles without bypass Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502...
  • Page 169: Environmental Specifications

    Immunity System Efficiency at Full Unity Power Factor Load and Nominal Input Voltage Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 0 to 40˚C without derating. The recommended operating temperature is 25˚C. Maximum 1500m (5000 ft) at 40_C without derating ---20 to +70˚C (prolonged storage above 40˚C...
  • Page 170 This Page Intentionally Left Blank. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 15--4 164201300 REV. G 061502...
  • Page 171: Appendix A --- Customer Information

    164201300---16 · 164201300---17 · 164201300---18 · 164201300---19 Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 Power Wiring Installation Notes Customer Interface Wiring Installation Notes Physical Features and Requirements Typical UPS System UPS System Configurations Oneline Drawing of UPS Cabinet...
  • Page 172 8 (1) VDC (Nominal) Amps AWG or kcmil(ea) 10 (1) Amps 27.8 AWG or kcmil(ea) 8 (1) POWER WIRING INSTALLATION NOTES SHEET: 164201300---1 DATE: 111501 Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 1 of 17...
  • Page 173 Full Load Current 3 , (1) Neutral, (1) gnd OUTPUT Minimum conductor size (number per  ) NOTE: Callout letter map to drawing #164201300---6 Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 Powerware 9330---20/15 (Without Options Cabinet) (0.95min.PF) (0.95min.PF) 3 , (1) Neutral, (1) gnd...
  • Page 174 Minimum Current Input Output (Amps) 27.8 41.6 14.4 55.5 19.2 27.8 41.6 14.4 55.5 19.2 POWER WIRING INSTALLATION NOTES SHEET: 164201300---1 DATE: 053001 Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 Size 3 of 17...
  • Page 175 3 , 1 Neutral, 1 gnd NOTE: Callout letter map to drawing #164201300---6 Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 Table E. Ratings & External Wiring Requirements for Powerware 9330 (10 kVA---20 kVA) Options Cabinet OUTPUT Transformer...
  • Page 176 2 (1) VDC (Nominal) Amps AWG or kcmil(ea) 3 (1) Amps AWG or kcmil(ea) 2 (1) POWER WIRING INSTALLATION NOTES SHEET: 164201300---1 DATE: 053001 Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 5 of 17...
  • Page 177 Full Load Current 3 , (1) Neutral, (1) gnd OUTPUT Minimum conductor size (number per  ) NOTE: Callout letter map to drawing #164201300---6 Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 Powerware 9330---40/35 (Without Options Cabinet) (0.95min.PF) (0.95min.PF) 3 , (1) Neutral, (1) gnd...
  • Page 178 Input Input Minimum Current Input Output (Amps) 69.4 28.8 33.6 38.5 69.4 28.8 33.6 33.5 POWER WIRING INSTALLATION NOTES SHEET: 164201300---1 DATE: 053001 Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 Size 7 of 17...
  • Page 179 3 , 1 Neutral, 1 gnd NOTE: Callout letter map to drawing #164201300---6 Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 Table L. Ratings & External Wiring Requirements for Powerware 9330 (25 kVA---40 kVA) Options Cabinet OUTPUT Transformer...
  • Page 180 Table R and U for conduit requirements. Drawings 164201300---8 through 164201300---12 show the location of the power cable terminals inside the UPS, Options, and Battery Cabinets. Table N. UPS Cabinet Power Cable Terminations Powerware 9330 (10 kVA---20 kVA) Terminal Function AC Input to UPS...
  • Page 181 Table O. UPS Cabinet Power Cable Terminations Powerware 9330 (25 kVA---40 kVA) Terminal Function AC Input to UPS Rectifier and Bypass (TB2) (TB2) (Single Input) (Single Input) AC Input to UPS Rectifier (CB1) (Dual Input) (Dual Input) AC Input To Bypass...
  • Page 182 Table P. Options Cabinet Power Cable Terminations Powerware 9330 (10 kVA---20 kVA) Terminal Function AC Input to UPS Rectifier Transformer (TB1) (TB1) AC Input To UPS Bypass Transformer Bypass Transformer (TB1) AC Output from Output Transformer Output Transformer to Critical Load...
  • Page 183 R. All 9330 products can accommodate a double size neutral. Conduit sizes were chosen from NEC Table C1, type letters RHH, RHW, RHW-2, TW, THW, THHW, THW-2.
  • Page 184 Table S. Power Cable Conduit Requirements Powerware 9330 (20 kVA) Powerware Voltage System 9330-20/20 9330-20/20 9330-20/20 9330---20/20 A ---14 Number of Terminal AC Input to UPS (A, B, C, Gnd) AC Input to Bypass (A, B, C, Neut, Gnd) Output...
  • Page 185 Table T. Power Cable Conduit Requirements Powerware 9330 (25 kVA -- 30 kVA) Powerware Voltage System 9330-40/25 9330---40/25 9330---40/25 9330---40/25 9330-40/30 9330-40/30 9330-40/30 9330---40/30 Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 Number of Terminal...
  • Page 186 Table U. Power Cable Conduit Requirements Powerware 9330 (35 kVA -- 40 kVA) Powerware Voltage System 9330-40/35 9330---40/35 9330---40/35 9330---40/35 9330-40/40 9330-40/40 9330-40/40 9330---40/40 A ---16 Number of Terminal AC Input to UPS (A, B, C, Gnd) AC Input to Bypass...
  • Page 187 When the optional Options Cabinet is used, source protection for the AC input should be treated as if you were supplying a 20 kVA three phase transformer for the Powerware 9330 (10 kVA---20 kVA) and a 40 kVA three phase transformer for the Powerware 9330 (25 kVA---40 kVA), to allow for inrush current.
  • Page 188 Rated battery current is computed at the computed voltage. A ---18 Output Voltage Rating 208V 480V 600V DESCRIPTION: POWER WIRING INSTALLATION NOTES DRAWING NO: 164201300---1 REVISION: DATE: Powerware 9330 (10 kVA- -40 kVA) Installation and Operation SHEET: 17 of 17 053001 164201300 REV. G 061502...
  • Page 189 RELAY 2 NC X---Slot 4 Terminal UTIL_FAIL ON_BYPASS BATTERY_LOW Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 Name Programmable UPS alarm. Activated by a remote dry Programmable UPS alarm. Activated by a remote dry contact closure.
  • Page 190 BUILDING ALARM #3 BUILDING ALARM #3 RETURN BUILDING ALARM #4 BUILDING ALARM #4 RETURN TERMINAL TB2 CUSTOMER INTERFACE WIRING INSTALLATION NOTES SHEET: 164201300---2 DATE: 061502 Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 2 of 5...
  • Page 191 X--- SLOT 4 RIBBON CONNECTOR (AS400 Slot) X--- SLOT 3 RIBBON CONNECTOR X--- SLOT 1 RIBBON CONNECTOR Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 CSB CUSTOMER INTERFACE COMMUNICATIONS SERVER BOARD (CSB) REFER TO DRAWING 164201300--- 8...
  • Page 192 Table Y. Summary Alarm Relay Contacts RELAY 2 RELAY 1 Maximum Carrying Current: 5A DESCRIPTION: DRAWING NO: REVISION: G CUSTOMER INTERFACE WIRING INSTALLATION NOTES SHEET: 164201300---2 DATE: 051502 Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 4 of 5...
  • Page 193 Remote EPO switch rating is 24 VDC, 1 Amp minimum. NOTE: This switch must be a dedicated switch not tied into any other circuits. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 Table Z Remote EPO...
  • Page 194 12 inches air circulation clearance Allow space for Options and Battery Cabinets DESCRIPTION: PHYSICAL FEATURES AND REQUIREMENTS DRAWING NO: 164201300---3 REVISION: Powerware 9330 (10 kVA- -40 kVA) Installation and Operation Weight Kg (lb) Installed Point Loading 6 at 73 (160) 9 at 93 (205)
  • Page 195 480/208, 600/208 35 KVA 480/480 208/208 480/208, 600/208 40 KVA 480/480 Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 0---40˚C (32---104˚F) 95%, noncondensing During Full Load Operation Powerware 9330 (10 kVA-- 40 kVA) Input/Output Voltage BTU/hr ¢...
  • Page 196 A ---26 OPTIONS CABINET (OPTIONAL) POWERWARE 9330 (10 kVA---20 kVA) DESCRIPTION: TYPICAL UPS SYSTEM DRAWING NO: REVISION: Powerware 9330 (10 kVA- -40 kVA) Installation and Operation BATTERY CABINET (OPTIONAL) CABINET SHEET: 164201300---4 DATE: 053001 164201300 REV. G 061502 1 of 2...
  • Page 197 Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 CABINET OPTIONS CABINET (OPTIONAL) POWERWARE 9330 (25 kVA---40 kVA) DESCRIPTION: TYPICAL UPS SYSTEM DRAWING NO: REVISION: G BATTERY CABINET (OPTIONAL) SHEET: 164201300---4 DATE: 061502 2 of 2...
  • Page 198 Dual Feed with Input and Output Isolation Transformers, Bypass Switch Isolation Transformers, Bypass Switch and Optional Distribution Panel UPS SYSTEM CONFIGURATIONS SHEET: 164201300---5 DATE: 111501 Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 1 of 2...
  • Page 199 Sheet 10 Sheet 10 NOTE 1: A bypass neutral feeder must be supplied. NOTE 2: Output Voltage must match Bypass Input Voltage. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 Powerware Vin / Vout Model 9330---40/25...
  • Page 200 REVISION: G BUILDING ALARMS GENERAL PURPOSE RELAYS X--- SLOT INTERFACE SERVER AC OUTPUT CRITICAL LOAD ONELINE DRAWINGS OF UPS SYSTEM SHEET: 164201300---6 DATE: 031502 Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 1 of 1...
  • Page 201 CONFIGURATION 12 CONFIGURATION 13 SINGLE FEED; INPUT TRANSFORMER; SINGLE FEED; INPUT TRANSFORMER; BYPASS SWITCH; WITHOUT DISTRIBUTION BYPASS SWITCH; WITH DISTRIBUTION Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 MAIN ISO XFMR BYPASS ISO XFMR EXT. WRAP...
  • Page 202 POWERWARE 9330 (10 kVA---20 kVA) DESCRIPTION: DRAWING NO: REVISION: INTER- - CABINET WIRING EXT. WRAP BYPASS OPTIONS CABINET SCHEMATICS SHEET: 164201300---7 DATE: 111501 Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 CABINET MAINS BYPASS AC LOADS 2 of 10...
  • Page 203 BYPASS SWITCH; WITHOUT DISTRIBUTION CONFIGURATION 15 CONFIGURATION 14 DUAL FEED; OUTPUT TRANSFORMER; DUAL FEED; OUTPUT TRANSFORMER; BYPASS SWITCH; WITH DISTRIBUTION BYPASS SWITCH; WITHOUT DISTRIBUTION Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 OPTIONAL BYPASS BREAKER OUTPUT XFMR...
  • Page 204 DRAWING NO: REVISION: INTER- - CABINET WIRING INPUT BREAKER EXT. WRAP BYPASS OPTIONS CABINET SCHEMATICS SHEET: 164201300---7 DATE: 111501 Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 CABINET MAINS BYPASS AC LOADS 4 of 10...
  • Page 205 DUAL FEED; INPUT AND OUTPUT TRANSFORMERS; BYPASS SWITCH; WITH DISTRIBUTION CONFIGURATION 17 DUAL FEED; INPUT AND OUTPUT TRANSFORMERS; BYPASS SWITCH; WITHOUT DISTRIBUTION Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 MAIN ISO XFMR BYPASS BREAKER...
  • Page 206 REVISION: INTER- - OPTIONAL CABINET WIRING INPUT BREAKER 150A BYPASS BREAKER 150A OPTIONS CABINET SCHEMATICS SHEET: 164201300---7 DATE: 111501 Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 CABINET MAINS BYPASS AC LOADS 6 of 10...
  • Page 207 WITHOUT DISTRIBUTION WITH DISTRIBUTION CONFIGURATION 10 CONFIGURATION 11 SINGLE FEED; BYPASS SWITCH; SINGLE FEED; BYPASS SWITCH; WITH DISTRIBUTION WITHOUT DISTRIBUTION Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 OPTIONAL BYPASS BREAKER 150A OUTPUT BREAKER 150A...
  • Page 208 POWERWARE 9330 (25 kVA---40 kVA) DESCRIPTION: DRAWING NO: REVISION: INTER- - CABINET WIRING EXT. WRAP BYPASS OPTIONS CABINET SCHEMATICS SHEET: 164201300---7 DATE: 111501 Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 CABINET MAINS BYPASS AC LOADS 8 of 10...
  • Page 209 SINGLE FEED; INPUT AND OUTPUT TRANSFORMERS; BYPASS SWITCH; WITH DISTRIBUTION CONFIGURATION 9 SINGLE FEED; INPUT AND OUTPUT TRANSFORMERS; BYPASS SWITCH; WITHOUT DISTRIBUTION Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 MAIN ISO XFMR OUTPUT XFMR...
  • Page 210 DRAWING NO: REVISION: INTER- - CABINET WIRING INPUT BREAKER 150A EXT. WRAP BYPASS OPTIONS CABINET SCHEMATICS SHEET: 164201300---7 DATE: 111501 Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 CABINET MAINS BYPASS AC LOADS 10 of 10...
  • Page 211: Front View

    NOTE: METAL SHIELD COVERING POWER WIRING TERMINALS AND BATTERY COMPARTMENT MUST BE REMOVED TO GAIN ACCESS TO WIRING TERMINALS. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 GROUND TERMINALS FRONT VIEW DESCRIPTION: LOCATION OF UPS CABINET TERMINALS...
  • Page 212 AC INPUT TO UPS RECTIFIER AND BYPASS (TB2) (SINGLE INPUT) AC INPUT TO BYPASS (TB2) (DUAL INPUT) NEUTRAL PHASE C SHEET: 164201300---8 DATE: 111501 Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 2 of 5...
  • Page 213: Left View

    UPS CABINET POWER TERMINALS LEFT VIEW Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 POWER WIRING WIREWAY DESCRIPTION: LOCATION OF UPS CABINET TERMINALS POWERWARE 9330 (10 kVA-- 20 kVA) DRAWING NO: 164201300---8 REVISION: INPUT BREAKER CB1...
  • Page 214 OUTPUT CONNECTIONS (REMOVE PANEL TO DRILL OR PUNCH CONDUIT HOLES.) LOCATION OF UPS CABINET TERMINALS POWERWARE 9330 (10 kVA-- 20 kVA) SHEET: 164201300---8 DATE: 111501 Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 4 of 5...
  • Page 215: Top View

    UPS CABINET CUSTOMER INTERFACE TERMINALS CUSTOMER INTERFACE CONDUIT LANDING PLATE (REMOVE PANEL TO DRILL OR PUNCH CONDUIT HOLES.) Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 COMMUNICATIONS SERVER BOARD (CSB) X---SLOT DEVICES TOP VIEW DESCRIPTION:...
  • Page 216 GROUND TERMINALS FRONT VIEW DESCRIPTION: LOCATION OF UPS CABINET TERMINALS POWERWARE 9330 (25 kVA-- 40 kVA) DRAWING NO: 164201300---9 REVISION: Powerware 9330 (10 kVA- -40 kVA) Installation and Operation BATTERY BREAKER CB2 INTERNAL BATTERIES SHEET: 1 of 6 DATE: 053001...
  • Page 217 AC INPUT TO BYPASS (TB2) (DUAL INPUT) DC INPUT FROM REMOTE BATTERY AC OUTPUT TO CRITICAL LOAD (TB3) FRONT VIEW DETAIL Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 PHASE A PHASE B PHASE C PHASE A...
  • Page 218 POWER WIRING WIREWAY DESCRIPTION: LOCATION OF UPS CABINET TERMINALS POWERWARE 9330 (25 kVA-- 40 kVA) DRAWING NO: REVISION: Powerware 9330 (10 kVA- -40 kVA) Installation and Operation INPUT BREAKER CB1 AC INPUT TO UPS RECTIFIER (CB1) (DUAL INPUT) (A, B, C)
  • Page 219 UPS CABINET CUSTOMER INTERFACE TERMINALS X---SLOT DEVICE INTERFACE PANELS X1 X2 X3 X4 Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 CUSTOMER INTERFACE ACCESS PANEL SERIAL PORT DESCRIPTION: DRAWING NO: REVISION: CUSTOMER CONVENIENCE OUTLET FOR MODEM 120VAC, 0.2 AMP...
  • Page 220 (REMOVE PANEL TO DRILL OR PUNCH CONDUIT HOLES.) DESCRIPTION: LOCATION OF UPS CABINET TERMINALS POWERWARE 9330 (25 kVA-- 40 kVA) DRAWING NO: 164201300---9 REVISION: Powerware 9330 (10 kVA- -40 kVA) Installation and Operation SHEET: 5 of 6 DATE: 053001 164201300 REV. G 061502...
  • Page 221 UPS CABINET CUSTOMER INTERFACE TERMINALS CUSTOMER INTERFACE ACCESS PANEL Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 COMMUNICATIONS SERVER BOARD (CSB) X---SLOT DEVICES X4 X3 X2 X1 EXTERNAL BATTERY CABINET POWER CONNECTOR DESCRIPTION: LOCATION OF UPS CABINET TERMINALS...
  • Page 222 QO OR QOB BREAKERS) GROUND TERMINALS DESCRIPTION: LOCATION OF OPTIONS CABINET TERMINALS POWERWARE 9330 (10 kVA-- 20 kVA) DRAWING NO: 164201300---10 REVISION: Powerware 9330 (10 kVA- -40 kVA) Installation and Operation BYPASS BREAKER AC OUTPUT BREAKER AC INPUT BREAKER MAINTENANCE BYPASS...
  • Page 223 OPTIONS CABINET POWER TERMINALS Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 INPUT OUTPUT TERMINAL STRIP TB1 (SEE SHEET 3 FOR DETAILS) DESCRIPTION: LOCATION OF OPTIONS CABINET TERMINALS POWERWARE 9330 (10 kVA-- 20 kVA) DRAWING NO:...
  • Page 224 TERMINAL STRIP TB1 A ---54 DESCRIPTION: LOCATION OF OPTIONS CABINET TERMINALS POWERWARE 9330 (10 kVA-- 20 kVA) DRAWING NO: 164201300---10 REVISION: Powerware 9330 (10 kVA- -40 kVA) Installation and Operation SHEET: 3 of 4 DATE: 053001 164201300 REV. G 061502...
  • Page 225 OPTIONS CABINET POWER TERMINALS Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 CONDUIT ENTRY AREA FOR OUTPUT FROM OPTIONAL DISTRIBUTION PANEL (REMOVE PANEL TO DRILL OR PUNCH CONDUIT HOLES.) REAR ENTRY CONDUIT LANDING FOR AC INPUT AND...
  • Page 226 QO OR QOB BREAKERS) A ---56 DESCRIPTION: LOCATION OF OPTIONS CABINET TERMINALS POWERWARE 9330 (25 kVA-- 40 kVA) DRAWING NO: 164201300---11 REVISION: Powerware 9330 (10 kVA- -40 kVA) Installation and Operation AC OUTPUT BREAKER BYPASS BREAKER AC INPUT BREAKER MAINTENANCE BYPASS...
  • Page 227 OPTIONS CABINET POWER TERMINALS Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 NEUTRAL TERMINALS INPUT OUTPUT TERMINAL STRIP TB1 (SEE SHEET 3 FOR DETAILS) GROUND TERMINALS DESCRIPTION: LOCATION OF OPTIONS CABINET TERMINALS POWERWARE 9330 (25 kVA-- 40 kVA)
  • Page 228 TERMINAL STRIP TB1 A ---58 DESCRIPTION: LOCATION OF OPTIONS CABINET TERMNALS POWERWARE 9330 (25 kVA-- 40 kVA) DRAWING NO: 164201300---11 REVISION: Powerware 9330 (10 kVA- -40 kVA) Installation and Operation PHASE DESIGNATION SHEET: 3 of 4 DATE: 053001 164201300 REV. G 061502...
  • Page 229 FOR AC INPUT AND OUTPUT CONNECTIONS (REMOVE PANEL TO DRILL OR PUNCH CONDUIT HOLES.) Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 DESCRIPTION: LOCATION OF OPTIONS CABINET TERMINALS POWERWARE 9330 (25 kVA-- 40 kVA) DRAWING NO:...
  • Page 230 LOCATION OF BATTERY CABINET TERMINALS POWERWARE 9330 (10 kVA-- 20 kVA) POWERWARE 9330 (25 kVA-- 40 kVA) DRAWING NO: 164201300---12 REVISION: Powerware 9330 (10 kVA- -40 kVA) Installation and Operation SHEET: 1 of 1 DATE: 111501 164201300 REV. G 061502...
  • Page 231: Ups Cabinet

    Dimensions are in millimeters and [inches] Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 UPS CABINET DESCRIPTION: UPS CABINET DIMENSIONS POWERWARE 9330 (10 kVA-- 20 kVA) DRAWING NO: 164201300---13 REVISION: SHEET: 1 of 2 DATE:...
  • Page 232 UPS CABINET Dimensions are in millimeters and [inches] DESCRIPTION: UPS CABINET DIMENSIONS POWERWARE 9330 (10 kVA-- 20 kVA) DRAWING NO: 164201300---13 REVISION: Powerware 9330 (10 kVA- -40 kVA) Installation and Operation SHEET: 2 of 2 DATE: 111501 164201300 REV. G 061502...
  • Page 233 Dimensions are in millimeters and [inches] Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 UPS CABINET DESCRIPTION: UPS CABINET DIMENSIONS POWERWARE 9330 (25 kVA-- 40 kVA) DRAWING NO: 164201300---14 REVISION: SHEET: 1 of 4 DATE:...
  • Page 234 Dimensions are in millimeters and [inches] A ---64 UPS CABINET DESCRIPTION: UPS CABINET DIMENSIONS POWERWARE 9330 (25 kVA-- 40 kVA) DRAWING NO: 164201300---14 REVISION: Powerware 9330 (10 kVA- -40 kVA) Installation and Operation SHEET: 2 of 4 DATE: 053001 164201300 REV. G 061502...
  • Page 235 Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 UPS CABINET Dimensions are in millimeters and [inches] DESCRIPTION: UPS CABINET DIMENSIONS POWERWARE 9330 (25 kVA-- 40 kVA) DRAWING NO: 164201300---14 REVISION: SHEET: 3 of 4 DATE:...
  • Page 236 UPS CABINET Dimensions are in millimeters and [inches] DESCRIPTION: UPS CABINET DIMENSIONS POWERWARE 9330 (25 kVA-- 40 kVA) DRAWING NO: 164201300---14 REVISION: Powerware 9330 (10 kVA- -40 kVA) Installation and Operation SHEET: 4 of 4 DATE: 071501 164201300 REV. G 061502...
  • Page 237: Options Cabinet

    Dimensions are in millimeters and [inches] Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 OPTIONS CABINET DESCRIPTION: OPTIONS CABINET DIMENSIONS POWERWARE 9330 (10 kVA-- 20 kVA) DRAWING NO: 164201300---15 REVISION: SHEET: 1 of 2 DATE:...
  • Page 238 OPTIONS CABINET Dimensions are in millimeters and [inches] DESCRIPTION: OPTIONS CABINET DIMENSIONS POWERWARE 9330 (10 kVA-- 20 kVA) DRAWING NO: 164201300---15 REVISION: Powerware 9330 (10 kVA- -40 kVA) Installation and Operation SHEET: 2 of 2 DATE: 053001 164201300 REV. G 061502...
  • Page 239 Dimensions are in millimeters and [inches] Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 OPTIONS CABINET DESCRIPTION: OPTIONS CABINET DIMENSIONS POWERWARE 9330 (25 kVA-- 40 kVA) DRAWING NO: 164201300---16 REVISION: SHEET: 1 of 2 DATE:...
  • Page 240 Dimensions are in millimeters and [inches] DESCRIPTION: OPTIONS CABINET DIMENSIONS POWERWARE 9330 (25 kVA-- 40 kVA) DRAWING NO: SHEET: 164201300---16 2 of 2 REVISION: DATE: 053001 Powerware 9330 (10 kVA- -40 kVA) Installation and Operation A ---70 164201300 REV. G 061502...
  • Page 241: Battery Cabinet

    Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 BATTERY CABINET Dimensions are in millimeters and [inches] DESCRIPTION: BATTERY CABINET DIMENSIONS POWERWARE 9330 (10 kVA-- 20 kVA) POWERWARE 9330 (25 kVA-- 40 kVA) DRAWING NO: REVISION:...
  • Page 242 Dimensions are in millimeters and [inches] A ---72 226.4 [8.9] DESCRIPTION: TYPICAL REMOTE EMERGENCY POWER OFF DRAWING NO: 164201300---18 REVISION: Powerware 9330 (10 kVA- -40 kVA) Installation and Operation KNOCKOUTS 1/2” CONDUIT (5 PLACES) SHEET: 1 of 2 DATE: 051502 164201300 REV. G 061502...
  • Page 243 [1.9] NOTE: Interface wiring and conduit between the Remote Emergency Power Off switch and the UPS are to be supplied by the customer. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 122.3 [4.8] 68.5 68.5 [2.7]...
  • Page 244 ON A SINGLE OR DOUBLE GANG ELECTRICAL BOX. Dimensions are in millimeters and (inches) REMOTE MONITOR PANEL DIMENSIONS 164201300---19 DATE: 051502 Powerware 9330 (10 kVA- -40 kVA) Installation and Operation 164201300 REV. G 061502 12.7 [0.5] SHEET: 1 of 1...
  • Page 245 If, in the opinion of Powerware, the Unit fails to meet published specifications and the defect is within the terms of this warranty, the Unit will be repaired or replaced at the option of Powerware with no charge for replacement parts. Labor required, to make the repairs or replacement installation, and travel costs incurred by Powerware’s representatives, is not included under the...
  • Page 246 This Page Intentionally Left Blank. Powerware 9330 (10 kVA- -40 kVA) Installation and Operation W--2 164201300 REV. G 061502...

Table of Contents

Save PDF