Install The Mast And Lift Cylinder Together - Skyjack SJ12 E Service Manual

Vertical mast lifts
Hide thumbs Also See for SJ12 E:
Table of Contents

Advertisement

Section 5 – Procedures
14. Remove and set aside the red knob and hex
standoff from the emergency lowering valve.
Hold the valve shaft with a wrench to keep it from
turning when you remove the hex standoff.
15. Remove and set aside the bolts and washers that
secure the mast to the chassis.
16. Attach hoist rings to opposite corners of mast 1.
17. Use lifting straps to lift the mast above the
chassis.
18. Set aside the mast.
241914ACA
84
5.3-5 Install the Mast and Lift Cylinder
Together
1. Use lifting straps and hoist rings to lift the mast
and lift cylinder and install it onto the chassis.
Make sure the holding valve coil faces the rear of
the machine.
2. Use the bolts and washers removed earlier to
secure the mast to the chassis.
Platform
SJ12 E, SJ16 E, SJ20 E

Advertisement

Table of Contents
loading

This manual is also suitable for:

Sj16 eSj20 e

Table of Contents