Section 5 – Procedures
11. Route the AC power cable towards the rear of the
machine and out the AC inlet hole.
12. Connect the AC power cable to the inlet.
Green wire to the green terminal
Black wire to the bronze terminal
White wire to the silver terminal
13. Use new pop rivets to secure the AC inlet to the
chassis.
241914ACA
86
14. Use the nut removed earlier to secure the green
ground wire from the AC inlet to the chassis
15. Use tie wraps to secure the AC power cable to the
existing cable bundles.
16. Install the platform. Refer to section
the
Platform.
Platform
5.2-2 Install
SJ12 E, SJ16 E, SJ20 E