Platform
6. At the rear of the machine, drill out the rivets that
secure the AC inlet to the chassis.
7. Pull out the AC inlet.
8. Disconnect the wires from the back of the AC
inlet.
9. Remove and set aside the nut that secures the
ground wire to the chassis. You may need to
remove the chassis cover to access the wire.
10. Cut the tie wraps that secure the AC power cable
to the cable carrier and existing cable bundles.
SJ12 E, SJ16 E, SJ20 E
11. Remove and set aside the mast cover and
hardware.
12. Disconnect the electrical cable from the holding
valve coil at the bottom of the lift cylinder.
13. Disconnect the hydraulic hose from the bottom of
the emergency lowering valve manifold. Cap or
plug the hose end and hydraulic fitting.
Section 5 – Procedures
241914ACA
83