The Hipot Start parameter is only used when connecting the HYAMP III with an
Associated Research Hipot tester. If GW is selected, the Hipot test will run after the
HYAMP III has completed its test. If G + W is selected, the Hipot test will run at the
same time as the HYAMP III.
The Hipot Start parameter directly controls the Start Output relay. Running in the
GW mode will momentarily close the Start Output relay at the end of the HYAMP III
test. Running in the G + W mode will momentarily close the Start Output relay at the
start of the HYAMP III test.
Cal-Alert (Calibration Alert)
The Cal-Alert feature alerts the user that the instrument is due for calibration. Turning
this parameter ON will activate the Cal-Alert function and when the date matches the
Alert Date, the instrument will display the Cal-Alert warning screen upon power up. If
the "Show this screen again?" function has been turned OFF at the Cal-Alert Warning
screen, this parameter will automatically be set to OFF.
Cal Date(Calibration Date)
Cal Date is a non-editable parameter that indicates the last date that calibration was
performed on the instrument. This parameter is updated at the time of calibration.
Cal Due (Calibration Due Date)
After a calibration is performed, the Cal Due Date is automatically set for 1 year after
the calibration date. This parameter may be overwritten to any date desired. Within
the Cal Due Date parameter are three separate fields, month, day, and year. Use the
"" soft key to select the field within the date you want to edit then use the "+" soft key
to change the numeric value. Once you change the value it is automatically stored.
NOTE: It is recommended that calibration should be performed at least once a
year.
Alert (Alert Date)
The Alert Date is like an alarm clock that will warn you in advance of the actual
Calibration Due Date. After a calibration is performed, the Alert Date is automatically
set for 11 months after the calibration date. For example, if the calibration is
performed on 12/15/2002 the Alert Date will automatically be set to 11/15/2003.
This parameter may be overwritten to any advanced date desired. Within the Alert
Date parameter are three separate fields, month, day, and year. Use the "" soft key
to select the field within the date you want to edit. Use the "+" soft key to change the
numeric value. Once you change the value it is automatically stored.
Date
Within the Set Date parameter are four fields, date format (mdy / dmy), month, day,
and year. Use the "" soft key to select the field within the date you want to edit. Use
26