Set points grid-tied
The set points during grid-tied operation are adjusted in the ASC. In the tree structure, the peak shaving, power export and fixed
power values can be selected and adjusted.

15.2 Power management system

In an integrated system, the power management selection is needed. The actual mode is transmitted on the power management
communication.
Table 15.1
Plant mode parameter
Parameter Range
Island mode
Fixed power
6071
Mains power export
Power management
Set points
The set points are communicated with the power management system. For the DG minimum load setting, refer to the same settings
as mentioned in the stand-alone system above.
COMMISSIONING GUIDELINES 4189341077D EN
Menu group Notes
For a power management system, this parameter must be set to Power
6070
management.