Chapter
DEIF control system commissioning
13.2, 13.3
Configure inverter type, IDs and baud rate
14
Emergency stop
15
Configure plant modes and set points
15.2
Configure minimum DG load
16
Configure spinning reserve alarms
17
Configure M-Logic with AUTO start/stop
18
Transducer setup
2.2
Before commissioning starts
Before commissioning the ASC-system the commissioning engineer must have an overview of the IP and ID plan, and an overview
of the power source data.
2.2.1
IP and ID plan
It is necessary to know all IDs and IP addresses of the plant. Below is an example. Please create a suitable IP plan in Excel so this
is ready before commissioning.
These parameters are needed for the commissioning:
•
Device
•
IP address
•
Modbus ID, monitoring
•
Modbus ID, control
•
Baud rate
Table 2.1
Example of selected communication data for commissioning
Device
ASC
ADFWEB HD67510
Inverter #1
Inverter #2
Inverter #3
Inverter #4
Inverter #5
Inverter #6
Inverter #7
Inverter #8
Inverter #9
DPM - MIC 4002
(mains)
DPM - MIC 4002 (generator#1)
COMMISSIONING GUIDELINES 4189341077D EN
IP address
Modbus ID, monitoring
-
10
172.170.10.2
-
172.170.10.10
10
172.170.10.11
11
172.170.10.12
12
172.170.10.13
13
172.170.10.14
14
172.170.10.15
15
172.170.10.16
16
172.170.10.17
17
172.170.10.18
18
-
1
-
2
Modbus ID, control
-
0
126
126
126
126
126
126
126
126
126
Baud rate
19200
19200
19200
19200
Page 7 of 58