8.2.5.3 Installing AC Output Power Cables in a Parallel System

● Install short-circuit plates for AC output circuit breakers.
● The three cables from the AC output circuit breaker to the power modules must
Procedure
Step 1 Install AC output power cables of the parallel box.
Issue 03 (2022-10-28)
NO TICE
be of the same length.