Table B-2 Definition of the stripping length of cables for a parallel box (parallel system scenario)
No.
One End
1
AC parallel
box
2
AC parallel
box
3
AC parallel
box
4
AC parallel
box
5
AC parallel
box
Issue 03 (2022-10-28)
Other End
1
PDC
L wire: 120 mm
(customer
N wire: 120 mm
side)
PE wire: 140 mm
AC input
L wire: 410 mm
N wire: 340 mm
PE wire: 240 mm
AC output
L wire: 115 mm
N wire: 220 mm
PE wire: 370 mm
PDB
L wire: 300 mm
(customer
N wire: 325 mm
side)
PE wire: 580 mm
Ground bar
N/A
(customer
side)
Copyright © Huawei Digital Power Technologies Co., Ltd.
B Preparing the Cable and Terminal
2
L wire: 16 mm
N wire: 14 mm
PE wire: 14 mm
L wire: 12 mm
N wire: 7 mm
PE wire: 7 mm
L wire: 12 mm
N wire: 7 mm
PE wire: 7 mm
L wire: 16 mm
N wire: 14 mm
PE wire: 14 mm
14 mm