8.3.6.2 Installing AC Input Power Cables in a Parallel System

Procedure
Step 1 Install AC input power cables of the parallel box.
Issue 03 (2022-10-28)
NO TE
● Install short-circuit plates for AC input circuit breakers.
● The three cables from the AC input circuit breaker to the power modules must be of the
same length.