Huawei PowerCube 5000 Installation Manual
Huawei PowerCube 5000 Installation Manual

Huawei PowerCube 5000 Installation Manual

Hide thumbs Also See for PowerCube 5000:
Table of Contents

Advertisement

PowerCube 5000 (SUN2000-150KTL-S0)
V100R003C00
Installation Guide
Issue
03
Date
2020-04-10
HUAWEI TECHNOLOGIES CO., LTD.

Advertisement

Table of Contents
loading

Summary of Contents for Huawei PowerCube 5000

  • Page 1 PowerCube 5000 (SUN2000-150KTL-S0) V100R003C00 Installation Guide Issue Date 2020-04-10 HUAWEI TECHNOLOGIES CO., LTD.
  • Page 2 Notice The purchased products, services and features are stipulated by the contract made between Huawei and the customer. All or part of the products, services and features described in this document may not be within the purchase scope or the usage scope. Unless otherwise specified in the contract, all statements, information, and recommendations in this document are provided "AS IS"...
  • Page 3: About This Document

    Indicates a potentially hazardous situation which, if not avoided, could result in equipment damage, data loss, performance deterioration, or unanticipated results. NOTICE is used to address practices not related to personal injury. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 4 Issue 03 (2020-04-10) Optimized the How Do I Prepare the WebUI Operating Environment section. Issue 02 (2018-12-07) Updated Setting Parameters (MDU). Issue 01 (2018-01-18) This issue is the first official release. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 5: Table Of Contents

    4.7 Installing a Smart ETH Gateway ...........................38 5 Installing Batteries and Cables..................... 41 6 Installing a BIM ........................43 7 Installing Cables ........................48 7.1 Installing a Dry Contact Signal Cable........................48 Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 6 10 Subsequent Operations ....................... 87 A How Do I Prepare the WebUI Operating Environment? ..........88 B Changing a User Password ....................93 C Preparing Terminals ......................95 D Acronyms and Abbreviations....................96 Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 7: Safety Information

    The "NOTICE", "CAUTION", "WARNING", and "DANGER" statements in this document do not cover all the safety instructions. They are only supplements to the safety instructions. Huawei will not be liable for any consequence caused by the violation of general safety requirements or design, production, and usage safety standards.
  • Page 8  Keep irrelevant people away from the equipment. Only operators are allowed to access the equipment.  Use insulated tools or tools with insulated handles, as shown in the following figure. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 9  To avoid electric shock, do not connect safety extra-low voltage (SELV) circuits to telecommunication network voltage (TNV) circuits. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 10: Personnel Requirements

    Do not power on the equipment before it is installed or confirmed by professionals. 1.2 Personnel Requirements  Personnel who plan to install or maintain Huawei equipment must receive thorough training, understand all necessary safety precautions, and be able to correctly perform all operations.
  • Page 11 When selecting, connecting, and routing cables, follow local safety regulations and rules. The static electricity generated by human bodies may damage the electrostatic-sensitive components on boards, for example, the large-scale integrated (LSI) circuits. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 12: Installation Environment Requirements

     Ensure that the equipment room provides good heat insulation, and the walls and floor are dampproof.  Install a rat guard at the door of the equipment room. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 13: Mechanical Safety

    Before hoisting objects, ensure that hoisting tools are firmly secured onto a load-bearing object or wall.  Ensure that the angle formed by two hoisting cables is no more than 90 degrees, as shown in the following figure. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 14 Do not climb higher than the fourth rung of the ladder from the top.  Ensure that your body's center of gravity does not shift outside the legs of the ladder. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 15 Metal shavings from drilling may short-circuit boards inside the equipment.  Obtain the consent from the customer, subcontractor, and Huawei before drilling.  Wear goggles and protective gloves when drilling holes. ...
  • Page 16: Battery Safety

    The site must be equipped with qualified fire extinguishing facilities, such as firefighting sands and powder fire extinguishers. To ensure battery safety and battery management accuracy, use batteries provided with the UPS by Huawei. Huawei is not responsible for any battery faults caused by batteries not provided by Huawei. Battery Installation Before installing batteries, observe the following safety precautions: ...
  • Page 17 Electrolyte overflow may damage the equipment. It will corrode metal parts and boards, and ultimately damage the boards.  If the electrolyte overflows, follow the instructions of the battery manufacturer or neutralize the electrolyte by using sodium bicarbonate (NaHCO ) or sodium carbonate Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 18 Use batteries within the allowed temperature range; otherwise, the battery performance and safety will be compromised.  Do not throw a lithium battery in fire.  When maintenance is complete, return the waste lithium battery to the maintenance office. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 19: Installation Preparations

    PowerCube 5000 (SUN2000-150KTL-S0) Installation Guide 2 Installation Preparations Installation Preparations 2.1 Tools This section lists the tools and instruments that you need to prepare for the installation. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 20: Preparing Cables

    Figure 2-1 Tools 2.2 Preparing Cables The cross-sectional area of a power cable depends on the current that will flow through the cable and the voltage drop allowed for the cable. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 21 The data listed in the table is the cable sizes applicable when the ambient temperature is 25° C. Use cables with larger cross-sectional areas if the ambient temperature is much higher or lower.  The battery cables should be able to resist a temperature of 90° C at least. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 22: Cabinet Installation Dimensions

    PowerCube 5000 (SUN2000-150KTL-S0) Installation Guide 2 Installation Preparations 2.3 Cabinet Installation Dimensions Figure 2-2 Installation dimensions (Single SUN2000) Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 23: Unpacking And Acceptance

    PowerCube 5000 (SUN2000-150KTL-S0) Installation Guide 2 Installation Preparations Figure 2-3 Installation dimensions (Parallel System) 2.4 Unpacking and Acceptance Context When transporting, carrying, and installing equipment: Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 24: Requirements For Laying Out Cables

    The total number of goods is consistent with Go to Step that on the packing list. The total number of goods is inconsistent Find the cause and contact the local Huawei with that on the packing list. office. Step 2 Check each packing case. If...
  • Page 25 The cable trough should be sealed and routed through the cable hole at the cabinet bottom.  Arrange the cables in order in the routing direction, and install cable clips. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 26 Circuit breakers or fuses are not allowed on ground cables.  No devices can be used as a part of ground cables.  All conductive metal components in the shell should properly connect to protection ground terminals. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 27: Installing The Cabinet

    Step 1 Unpack the cabinet. Step 2 Mark the position of the cabinet based on the delivered marking-off template. Figure 3-1 Marking mounting holes Step 3 Drill holes and install expansion sleeves. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 28 Figure 3-2 Drilling a hole and installing an expansion sleeve (1) M12 bolt (2) Spring washer (3) Flat washer (4) Expansion sleeve (5) Expansion nut (6) Concrete floor Step 4 Remove the rear panel of the cabinet. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 29 PowerCube 5000 (SUN2000-150KTL-S0) Installation Guide 3 Installing the Cabinet Figure 3-3 Removing the rear panel Step 5 (Optional) Install the cabinet mount. Figure 3-4 Installing the cabinet mount Step 6 Install the cabinet. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 30 Unscrew the connecting kits at the front and rear of the cabinet, align them with the reserved holes that can connect the two SUN2000s and then use screws to tighten the connecting kits to the cabinet according to the following figures. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 31 PowerCube 5000 (SUN2000-150KTL-S0) Installation Guide 3 Installing the Cabinet Figure 3-6 Installing connecting kits Step 8 Install the waterproof panel on the top of the cabinet. Remove the waterproof panel bracket. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 32 3 Installing the Cabinet Figure 3-7 Removing the waterproof panel bracket Install the waterproof panel bracket on the top of the cabinet. Figure 3-8 Installing the waterproof panel bracket Install the waterproof panel. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 33: Installing An Isolation Transformer

    Slightly tighten the expansion bolt and vertically insert it into the hole. Knock the expansion bolt using a rubber mallet until the expansion sleeve is fully inserted into the hole. Partially tighten the expansion bolt. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 34 Figure 3-10 Drilling a hole and installing an expansion sleeve (1) M12 bolt (2) Spring washer (3) Flat washer (4) Expansion sleeve (5) Expansion nut (6) Concrete floor Step 5 Install the isolation transformer. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 35 Step 6 Install the waterproof panel on the top of the isolation transformer. Remove the waterproof panel bracket. Figure 3-12 Removing the waterproof panel bracket Install the waterproof panel bracket on the top of the isolation transformer. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 36 PowerCube 5000 (SUN2000-150KTL-S0) Installation Guide 3 Installing the Cabinet Figure 3-13 Installing the waterproof panel bracket Install the waterproof panel. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 37: Installing A Cabinet Ground Cable

    Step 2 Route the ground cable and connect it to the ground bar. Ensure that the ground cable is installed securely. If devices are not properly grounded, damage to devices or personal injury may occur. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 38 Installation Guide 3 Installing the Cabinet Figure 3-15 Installing the ground cable (single SUN2000) (1) Site ground bar Figure 3-16 Installing the ground cable (Parallel System) (1) Site ground bar ----End Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 39: Installing Components

    PowerCube 5000 (SUN2000-150KTL-S0) Installation Guide 4 Installing Components Installing Components 4.1 Reference for Component Installation Positions Figure 4-1 Reference for component installation positions Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 40: Installing A Bps

    4.3 Installing an HSU Procedure Step 1 Unlock the positioning lock on the HSU. Step 2 Install the HSU on the guide rails. Step 3 Lock the positioning lock on the HSU. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 41: Installing An Nim01C3

    Step 2 Gently insert the NIM01C3 into the slot along the guide rails. Step 3 Push the handle leftwards and tighten the screws. The NIM01C3 must be installed in the upper slot. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 42: Installing A Dg Interface Module (Gim01C)

    Tighten the captive screws at both ends of the GIM01C panel to a torque of 0.6 N•m. The GIM01C must be installed in the slot under the installation slot for the communications expansion module. Otherwise, the GIM01C cannot work properly. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 43: Installing An Ibox

    Step 1 Connect the antenna provided with the iBOX to the RF_Z port on the iBOX. Step 2 Attach the fastener to the wall. Step 3 Clamp the iBOX to the fastener. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 44: Installing A Smart Eth Gateway

    Step 4 (Optional) If multiple iBOXs are required, install the other iBOXs in the same way. ----End 4.7 Installing a Smart ETH Gateway Procedure Step 1 Clamp the smart ETH gateway to the mounting bracket at the bottom of the cabinet. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 45 Connect one end of the cable to the ground screw on the smart ETH gateway. Connect the other end to the ground screw in the lower left corner of the cabinet. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 46 Figure 4-8 Connecting a ground cable to the smart ETH gateway Step 3 Connect power cables to the smart ETH gateway. Figure 4-9 Connect power cables to the smart ETH gateway ----End Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 47: Installing Batteries And Cables

    Do not use a metal to simultaneously touch two or more battery terminals or simultaneously touch a battery terminal and a grounded object (such as the battery compartment). Otherwise, short circuits will occur, causing sparks or explosion. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 48 Secure battery cables to the torque specified in this chapter. Loose battery bolt connections will cause batteries to be burnt. For details about battery and cable installation, see the documents delivered with the batteries. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 49: Installing A Bim

    Step 1 (Optional) Remove the insulation cover from a battery. Step 2 Connect the negative and positive cables of the BIM to the negative and positive terminals of the battery respectively. The battery appearance is for reference only. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 50 Step 3 Connect the other end of the cables to the pin port on the BIM. Step 4 Strip the adhesive tape from the BIM fastener. Step 5 Attach the BIM to the battery. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 51 Step 1 Remove the insulation cover from a battery. Step 2 Connect the negative and positive cables of the BIM to the negative and positive terminals of the battery respectively. The battery appearance is for reference only. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 52 Step 3 Connect the other end of the cables to the pin port on the BIM. Step 4 Strip the adhesive tape from the BIM fastener. Step 5 Attach the BIM to the battery. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 53 Figure 6-7 Installing a BIM (battery 1) Figure 6-8 Installing a BIM (battery 2) Step 6 (Optional) Reinstall the insulation cover for the battery. Step 7 Install other BIMs in the same way. ----End Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 54: Installing Cables

    Step 3 Put away the screwdriver and check that the signal cable is securely connected to the dry contact. Figure 7-1 Installing a dry contact signal cable (1) Contact plate (2) Dry contact ----End Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 55: Installing The Communications Cables

    Figure 7-3 Installing the communications cable (1) Smart ETH gateway Step 3 Cover a PVC corrugated pipe over the cable parts outside the cabinet and secure the PVC corrugated pipe to the cable hole. ----End Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 56: Wireless Networking

    Step 3 Connect the antenna to the ANT port on the NIM01C3. Before installing the antenna, remove the plastic shell from the antenna installation base to ensure magnetic adherence. Figure 7-5 Installing a wireless antenna ----End Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 57: Installing Cables Between Two Sun2000-150Ktl-S0 Cabinets

    If two SUN2000-150KTL-S0 cabinets are deployed, perform the following steps to install cables. Procedure Step 1 Install communications cables between ECMs. Figure 7-6 Installing communications cables between ECMs Step 2 Install a communications cable between ECC500Ss. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 58 Step 3 Install the EPO control cable. Remove the NC cable of EPO on the MUS01C in cabinet 1. Remove the EPO/-1 and EPO/-2 cables on the contacts of the emergency stop button. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 59 Figure 7-8 Remove the EPO cable in cabinet 1 Remove the 12V cable of EPO on the MUS01C in cabinet 2. Remove the EPO/-2 cable on the contact of the emergency stop button. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 60 Install auxiliary contacts at the bases on the rear of the emergency stop buttons in cabinets 1 and 2. Figure 7-10 Installing auxiliary contacts Install the parallel EPO control cable based on the cable label and diagram. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 61: Installing Cables Between The Sun2000-150Ktl-S0 And The Isolation Transformer

    After startup, press the emergency stop buttons in cabinets 1 and 2. The two cabinets should stop. ----End 7.4 Installing Cables Between the SUN2000-150KTL-S0 and the Isolation Transformer Procedure Step 1 Install surge protection, high-temperature, and overtemperature alarm signal cables between the SUN2000-150KTL-S0 and the isolation transformer. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 62 In this example, alarm cables are installed for an 80 kVA isolation transformer. Step 2 Install AC power cables between the SUN2000-150KTL-S0 and the isolation transformer. The AC input neutral wire of the isolation transformer must not be grounded. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 63 PowerCube 5000 (SUN2000-150KTL-S0) Installation Guide 7 Installing Cables Figure 7-13 Installing AC power cables (one SUN2000-150KTL-S0 cabinet) Figure 7-14 Installing AC power cables (two SUN2000-150KTL-S0 cabinets and 400 kVA isolation transformer) ----End Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 64: Installing An Ibox And Cables

    Figure 7-15 Installing the iBOX power cable (48 V) Step 2 Install the iBOX communications cable. Figure 7-16 Installing the iBOX communications cable Step 3 (Optional) Cascading cables should be installed if there are multiple iBOXs in the system. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 65 Address iBOX 1 iBOX 2 iBOX 3 iBOX 4 iBOX 5 iBOX 6 iBOX 7 iBOX 8 iBOX 9 iBOX 10 iBOX 11 iBOX 12 iBOX 13 iBOX 14 iBOX 15 Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 66: Installing Pv Input Power Cables

    Secure the other end of the DC input power cables to the output terminal in the SJB. Figure 7-18 Installing PV input power cables One PV input is used as an example. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 67: Installing Battery Input Power Cables

    Step 3 Install the negative battery string cable at the BAT- screw in the cabinet. Step 4 Install the positive battery string cable at the BAT+ screw in the cabinet. Figure 7-19 Installing battery input power cables (1) Battery switch box Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 68: Installing A Battery Temperature Sensor

     The battery temperature sensor probe must not be in direct contact with a metal surface. Figure 7-20 Securing a battery temperature sensor Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 69: Installing Ac Input Power Cables

    Step 1 Prepare a suitable length cable based on site requirements. Install a cord end terminal or an OT terminal on each end of the cable. Step 2 Install AC input power cables. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 70 In the parallel connection scenario, the length and model of cables from cabinets to the DG must be the same. Step 3 Cover a PVC corrugated pipe over the cable parts outside the cabinet and secure the PVC corrugated pipe to the cable hole. ----End Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 71: Installing Ac Output Power Cables For The Isolation Transformer

    Step 2 Secure the other end of the AC output power cables to the corresponding AC output circuit breaker. Figure 7-24 Installing AC output power cables for the isolation transformer (1) Site ground bar Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 72 PowerCube 5000 (SUN2000-150KTL-S0) Installation Guide 7 Installing Cables A residual leakage protection device needs to be added to the AC device connected to the AC output of the isolation transformer. ----End Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 73: Installation Verification

    □ Yes □ No There are no unnecessary adhesive tape or cable ties on cables. □ Yes □ No There are no adhesive tapes, cable ties, paper scraps, or packing materials around the cabinet. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 74 The cable tie tails on indoor cables are cut smoothly from the root, and the cable tie tails on outdoor cables are cut with a margin of 3 mm to 5 mm. □ Yes □ No Unused ports are protected. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 75: Power-On And Commissioning

    The battery supply is connected preferentially at night or when PV energy is insufficient. Required tools such as a clamp meter and insulation gloves are available. Procedure Step 1 Confirm as follows: Turn the PV input switches in the cabinet to OFF. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 76 Switch the battery circuit breakers to ON. Hold down the battery startup button for 5s. Observe the power indicator on the front panel of the HSU. If the indicator is steady green, the HSU works properly. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 77 PowerCube 5000 (SUN2000-150KTL-S0) Installation Guide 9 Power-on and Commissioning Figure 9-1 BATT Start (1) BATT Start ----End Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 78: Connecting The Pv Power Supply

    Step 4 Check that the output voltage of the DG is in the range of 400 V AC to 415 V AC. Step 5 Turn the AC input switch to ON. ----End 9.2 Setting Parameters (MDU) Procedure Step 1 Settings wizard (power on for the first time). Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 79 The value of the master device when Single/Parallel is set to is 1 and the slave device is 2. Parallel. Battery Type Set based on site requirements. NOTE Configurable type: TCB-A/SCB-A/DCB-A/High- Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 80 Table 9-5 Setting the System Param. 3 Path Parameters Setting Settings Wizard Output Volt Level (V) Set based on site requirements. NOTE Configurable level: 380/400/415 Output Volt Adjust (V) Set based on site requirements. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 81 Table 9-6 Setting the System Param. 4 Path Parameters Setting Settings Wizard DG Rated Power (kVA) Set based on site requirements. DG Limited Power Point Set based on site requirements. Set the Network Param. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 82  is the start/stop button used to control system output. Step 3 When the SMU is running properly, you can choose the following menus to change the MDU language. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 83 Communication assigned by the network administrator. Step 6 Set NetEco configuration parameters. In a parallel system, this parameter needs to be set only for the master unit. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 84: Connecting The Load Power Supply

    None Basic Param. NOTE The transformer high temperature alarm is shielded. ----End 9.3 Connecting the Load Power Supply Procedure Step 1 Turn the isolation switch in the isolation transformer to ON. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 85 The system output is restored 10 minutes after the battery supply is reconnected. Step 3 Access the MDU main menu, and then hold down the start/stop button , to control system output. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 86: Webui

    Step 2 Connect the FE port on the SMU by using a network cable. Figure 9-5 Connecting a Communications Cable (1) FE port ----End 9.4.2 Setting Parameters Procedure Step 1 Apply to the site or equipment room network administrator for a fixed IP address. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 87: Logging In To The Webui

    255.255.255.0, and default gateway to 192.168.0.1 on the PC. Step 2 Enter https://Monitoring local IP address (for example, https://192.168.0.10) in the address box of the browser, and then press Enter to access the WebUI login page. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 88: Setting Ibox Parameters(Optional)

    Change the preset password when you first log in to ensure system security. The method about how to change the password, see Changing a User Password. ----End 9.5 Setting iBOX Parameters(Optional) Procedure Step 1 Log in to the WebUI and perform iBOX port configuration. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 89 Figure 9-7 iBOX port configuration Set port configuration parameters based on the connected iBOX. Step 2 Set iBAT parameters. Figure 9-8 Setting iBAT parameters Set iBAT parameters based on the connected iBAT. ----End Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 90: Cim And Bim Networking

    BIM turns from steady red to blinking green at super short intervals and then blinking green at long intervals at last, indicating that the BIM searches for and connects to the CIM network. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 91: Shutdown And Power-Off

    Ensure that the output load is transferred or there is no major load so that system power-off is allowed. Once the integrated equipment is shut down, there is no power output from the output end. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 92: Shutting Down And Powering Off A Parallel System

    Step 2 Turn off all AC output switches, battery string switches, and isolation transformer disconnectors. Step 3 Turn off the solar input switch and AC input switch. Step 4 The loads power off completely. The control panel and indicators turn off. ----End Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 93: Subsequent Operations

    Step 4 Check whether the paint on the surface of the cabinet is intact. Repair any damaged paint. Step 5 Lock the cabinet door and hand over the key to the administrator. Step 6 Ensure that the site is clean before you leave the site. ----End Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 94: A How Do I Prepare The Webui Operating Environment

    To cancel proxy server settings, perform the following steps: Open Internet Explorer. Choose Tools > Internet Options. Choose Connections tab, click LAN Settings. Clear Use a proxy server for your LAN. Canceling proxy server settings Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 95 Export historical logs, historical data, statistics, and battery test records.  Upload system configuration files.  Download system configuration files.  Upgrade software. To set Internet Explorer security, perform the following steps: Open Internet Explorer. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 96 Initialize and script ActiveX controls not marked as safe for scripting Allow previously unused ActiveX controls to run without prompt − − Include local directory path when uploading files to a server Automatic prompting for file downloads − Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 97 PowerCube 5000 (SUN2000-150KTL-S0) Installation Guide A How Do I Prepare the WebUI Operating Environment? Internet Explorer security setting 4 Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 98 A How Do I Prepare the WebUI Operating Environment? Click OK. Click the Advanced tab, and select Use SSL 3.0, Use TLS 1.0, Use TLS 1.1, and Use TLS 1.2. Internet Explorer security setting 5 Click OK. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 99: B Changing A User Password

    Step 1 Log in to the WebUI and choose Maintenance > User management. The user management page is displayed. Step 2 Select the user whose password needs to be changed and click Modify. The dialog box for modifying user information is displayed. Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 100 The password must be different from the previous two passwords.  The password must be different from the user name or its reverse. Step 4 Set Password of Current Login User and click Submit. ----End Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 101: C Preparing Terminals

    Figure C-1 Preparing a cord end terminal (1) Cable (2) Cord end terminal (3) Crimping tool Figure C-2 Preparing an OT terminal (1) Cable (2) OT terminal (3) Heat shrink tubing (4) Hydraulic pliers (5) Heat gun Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 102: D Acronyms And Abbreviations

    Acronyms and Abbreviations alternating current direct current diesel generator energy control center energy control module emergency power-off general packet radio service GPRS MPPT maximum power point tracking Network Ecosystem NetEco photovoltaic module Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.
  • Page 103 PowerCube 5000 (SUN2000-150KTL-S0) Installation Guide D Acronyms and Abbreviations solar junction box site monitoring unit status of health surge protection device user interface module Universal Serial Bus Issue 03 (2020-04-10) Copyright © Huawei Technologies Co., Ltd.

This manual is also suitable for:

Sun2000-150ktl-s0

Table of Contents