Stripping Length - Huawei iSitePower-M ISP-M-MAB05B1 Manual

Intelligent power mate
Table of Contents

Advertisement

iSitePower-M V100R002C00
User Manual (MAP05A1, MAB05B1)
Figure B-3 Preparing a PV input power cable
B.4 Stripping Length
Figure B-4 Stripping length
Table B-1 Definition of the cable stripping length (standard scenario)
No.
One End
1
PV input
ports
2
AC output
3
AC output
4
Ground point
Issue 03 (2022-10-28)
Other End
1
DC switch
N/A
(customer
side)
PDB
100 mm
(customer
side)
PDB
75 mm
(customer
side)
Ground bar
N/A
(customer
side)
Copyright © Huawei Digital Power Technologies Co., Ltd.
B Preparing the Cable and Terminal
2
8–10 mm
PE wire: 7 mm
L/N wire: 17 mm
PE wire: 7 mm
L/N wire: 17 mm
7 mm
164