Device installation flow
The installation flows for SR6602-I and SR6602-IE gateways are as describe in Figure1-1.
Figure1-1 Device installation flow
On a rack
Start
Install the device
Ground the device
Install internal removable
components
Install external removable
components
Connect cables
Verify the installation
Power on the device for the
first time
Operating correctly?
Yes
End
1-1
On a workbench
No
Troubleshoot the device